Informs of Delay in Installation of E-field Sys Due to Contamination in Unit 1 Hcpi Area.Work on Intrusion & Perimeter Fence Alarm Sys Halted.No Further Completion Date Estimate Available
ML19338E562
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 11/10/1976
From: Bolger R
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19338E561 List:
References
NUDOCS 8010030349
Download: ML19338E562 (1)


Text

one F r t t ak n'ai Prza. Chicago. Ilun Acacess R: ply f(" :'ost Othc] Box 767 Chicago, Illinois 390 l-November 10, 1976 Mr. James G. Keppler, Director Office of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission i

799 Roosevelt Road y

Glen Ellyn, Illinois 60137

!~

Subject:

Dresden Station Units 1, 2,

and 3 IE Security Inspection Reports dated August 19, 1976 l

NRC Docket Nos. 50-10/237/249 Reference (a) :

R. L. Bolger Letter to J. G. Keppler dated October 14, 1976 - NRC Docket Nos. 50-10/237/249.

i

Dear Mr. Keppler:

In response to the October 5, 1976 meeting at Dresden (a) estimated Station with members of your staff, Reference "E-Field" 1976 as the date for completion of the December 1, Due to contamination system in the Dresden Unit 1 HPCI area.

installation of the discovered in the HPCI construction area, It will not intrusion alarm system has been halted.

"E-Field" be completed by December 1, 1976, and no further estimate is available for a completion Gate.

The existing perimeter fence "E-Field" alarm and alarm system will not be altered until the system is installed.

You will be advised of revised installation schedule when available.

Please address any questions to this office.

Very truly yours,

(

R. L. Bolger Assistant Vice President 8010030 3 f,'0V 111976