ML19338E036

From kanterella
Jump to navigation Jump to search
Responds to NRC 800617 ltr.SOP-30 Will Be Revised & Implemented by 800829 Resulting in Full Compliance.Ref IE Insp Repts 50-518/80-09,50-519/80-09,50-520/80-09 & 50-521/80-09
ML19338E036
Person / Time
Site: Hartsville  
Issue date: 08/22/1980
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8009240357
Download: ML19338E036 (1)


Text

_

.u.

  • I

[/d TENNECCEE VALLEY AUTHORITY

[d 4/I CHATTANOOGA. TEy$c r,c w ~.

4/7 mnp 37401j 400 chestnut Street Tower II

$/

11 Oc 28 P1:32 August 22, 1980 Mr. James P. O'Reilly, Director

/>ffice of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303

Dear Mr. O'Reilly:

TVA's response to C. E. Murphy's June 17, 1980, letter, RII:PKV 50-518/80-09, -519/80-09, -520/80-09, -521/80-09 was submitted on July 9, 1980. As discussed with NRC-0IE, Region II Inspector R. W. Wright on AuEust 20, 1980, TVA has not completed revision i

or issuance of SOP-30 p.a committed to by August 8,1980. We now plan to have SOP-30 revised and implemented by August 29, 1980, at which tient we will be in full compliance.

If you have any questions regarding this subject, please call Jim Domer at FTS 857-2014.

i Very truly yours, TENNESSEE VALLEY AUTHORITY

. M. Mills, Man ger ~

Nuclear Regulation and Safety 4

1 OFFICIAL COPY 800924 0 3 5 T An Equal Opportunity Employ"

,