Notification of 801009 & 10 Meetings W/Util in Mokane & Fulton,Mo to Discuss NRC Case Load Forecast
ML19338D810
Person / Time
Site: Callaway  Ameren icon.png
Issue date: 08/29/1980
From: Stark R
Office of Nuclear Reactor Regulation
To: Youngblood B
Office of Nuclear Reactor Regulation
References
NUDOCS 8009230770
Download: ML19338D810 (6)


Text

4

~

l c

j, UNITED STATES

'$k,

-- 3 NUCLEAR REGULATORY COMMISSION

. WASMNGTON, D. C. 20555

  • A AUG 2 91964 Docket Nos.: 50-483 and 50-486 i

MEMORANDUM FOR:

B. J. Youngblood, Chief, Licensing Branch No.1, DL FROM:

Richard M. Stark, Project Manager, Licensing Branch No.1, DL

SUBJECT:

CALLAWAY 1 AND 2 CASE LOAD FORECAST DATE AND TIME:

October 9 and 10,1980 8:00 AM - 5:00 PM LOCATION:

Mokane Lions Club Mokane, Missouri 65059 and Callaway Site Fulton, Missouri PURPOSE:

The NRC case load forecast panel meeting and site visit for the Callaway 1 and 2 plants (see agenda)

PARTICIPANTS:

NRC Staff W. Lovelace, R. Stark, W. Hansen Union Electric Comoany A. Passwater c b u.

/

Richard M. Stark, Project Manager Licensing Branch No. 1 Division of Licensing NOTE: Menters of the public wishing to attend should contact Richard M. Stark at 301-492-7238 by September 15, 1980 so that arrangements can be made for their attendance.

  • ""***o 7 7D

^

?-_

=

CALLAWAY UNIT ONE CASELOAD FORECAST PANEL SITE VISIT MEETING AGENDA 1.

Overview of project construction schedule including progress and major milestones ccmpleted since Caseload Panel visit of November,1979, current problems and any anticipated problem areas that may imcact~ the current projected fuel load date.

2.-

Detailed review and current status of design and engineering y

effort (by major discipline) including any potential problems i

that may arise from necessary rework.

3. _ Detailed review and current status of procurement activities including valves, pipe, instruments, cable, major components, etc.
4. - Actual and proposed craft wo-k force (by major craf t), craft availability, prcductivity, potential lacor negotiations and problems.

5.

Detailed review and cur ent status of all large and small bore pipe hangers, restrair.cs,. snubbers, etc., including design, rework, procurement, fabrication, delivery and installation, j

6. _ Detailed review of project schedule identifying critical path items, near critical items, amount of float for various activities, the current critical path to fuel loading, methods of implementation of corrective action for any activities with negative float, and provisions for contingencies.

The estimated project percent complete'as of September 30, lg80.

7.

Detailed review and current status of bulk quantities including current estimated quantities, quantities installed to date, quantities scheduled to date, current percent complete for each, actual versus forecast installation rates, and basis for figures.

(a) Concrete (CY)'

(b) ?rocess Pipe (LF)

Large Bore Pipe (2 1/2" and larger)

Small Bare Pipe (2" and smaller)

(c) YardPipe-(LF)

(d)' Large Bore Pipe Hangcts, Restraints, Snubbers (ea)

~

~

' ~'

~

~~

2 1

(e) Small Scre Pipe Hangers, Restraints (ea)

(f) Cable Tray (LF)

(g) Total Conduit (LF)

(h) Total Exposed Metal Conduit (LF)

(1) Cable (LF)

Power Control Security Instrumentation Plant Lighting (j) Tenninations (ea)

Power Control Security Instrumentation Plant Lighting (k) Electrical Circuits (ea)

Power Control Security (1) Instrumentation (ea) 8.

Detailed review and current status of preparation of preep test procedures, integration of preop test activities with construction schedule, system turnover schedule, preop test schedule, current and proposed preop test program manpower.

(a) Total number of procedures required for fuel load.

(b) Number of draft procedures not started.

(c) Number of draft procedures being written.

(d) Number of procedures approved.

(e) Number of procedures in review.

(fl Total number of preop tests required for fuel load.

(g) Number of preap tests ccmpleted.

(h).. Number cf preop tests currently in progress.

(i) Numbe" re systems turned over to start-up.

r

r;-.

j;,

9.

Detailed discussion of potential schedular influence due to changes attributed.to NUREG-0660, NUREG-0694 and other recent licensing requirements.

10. Site tour and observation of construction activities.

(

i i

G

h5

;. -.l-

?.

h.

A Mr'. J. ' K. B ryan Vice President - Nuclear Union Electric Company P. O. Box 149 St. Louis, Missouri F3166 cc:

Mr. Nicholas A. Petrick Executive Director - SNUPPS 5 Choke Cherry Road Rockville, Maryland 20850 Gerald Charnoff, Esq.

Shaw, Pittman, Potts, Trowbridge & Madden 1800 M Street, N.W.

Washington, O. C.

20036 Mr. J. E. Birk Assistant to.the General Counsel Union Electric Company P. O. Box 149 St. Louis, Missouri 63166 Dr..Vern Starks Route 1, Box-863 Ketchikan, Alaska 99901 Ms. Treva Hearn, Assi tint General Counsel Missouri Public Service Commission P. O. Box 250 Jefferson City, Missouri 65102

~

Resident Inspector.

U. S. Nuclear Regulatory Connission P. 0. Box 1748 Jefferson City, Missouri 65101 Mr. D. F. Schnell Manager - Nuclear Engineering Union Electric Company

.P. 0. Box 149' St. Louis, Missouri 63166

AUG 2 91980 MEETING NOTICE DISTRIBUTION Occket File J. Stol:

S. Hanauer Loca r P. Collins TIC

0. Vassallo NSIC
0. Ziemann Branch File R. Mattson H. Denton R. Schroeder E. Case K. Kniel
0. Eisenhut D. Skovhol t R. Purple G. Knighton T. Novak M. Ernst S. Varga R. Baer T. Ipcolito C. Berlinger R. A. Clark S. Israel R. Reid ACRS (16)

R. Tedesco Attorney, OELD J. Youngblood OIE (3)

A. Schwencer 050 (7)

Chief, Licensing Branch 13 Project Manager R. u e.,rv J. R. Miller Licensing Assistant M. Rusnorcok G. Lainas Receotionist D. Crutchfield TERA Chief, Systemic Evaluation Program Branch, J. LeCoux, I.EE Chief, Ocerating Reactors Assessment Branch R. Vollmer IAE Headauarters R. Bosnak I&E Region I F. Schauer ISE Reoion II R. E. Jackson ISE Region III G. Lear 14E Recion IV V. Noonan I&E Region V

5. Pawlicki V. Senaraya NRC Particioants:

I. Ros:toczy W. Lnvelace, R. Stark, W. Hansen W. Haass D. Muller R. Ballard W. Regan J. D. Sal t: man D. Ross P. Check R. Satterfield O. Parr bec: Aoplicant & Service List F. Rosa W. Butler

~

W. Kroger R. W. Hous ton T. Murphy W. Gammill L. Rubenstein T. Socis Chief, Cnre Performance Branch S. Grines H. Collins F. Pagano Emergency Precaredness Develoonent Branch