.e TENNESSEE VALLEY AUTHORf TY CH ATT ANOOG A. TE N N EGSEE 37401 500A Chestnut Street Tower II September 3, 1980 Director of Nuclear Reactor Regulation Attentior.:
Pr. A. Schwencer, Chief Licensing Branch No. 2 Division of Licensing U.S. Huelcar Regulatory Cor. mission Washington, DC 20555
Dear Isr. Schwencer:
In the I:ntter of the Application of
)
Docket No. 50-327 Tennessco Valley Authority
)
Enclosed is a status report on all licensing itens identified in the draft full powcr license transmitted from 11. R. Denten to the NRC Commissioners on August 20, 1980, as requiring cccpletion before exceeding 5 percent power operation.
Very truly yours, TELNESSEE VALLEY AUI!!ORITY J. L. Cross Executive Assistant to the
!!anager of Pcwcr Sworn to and subscri 64 before ne Lclcayof M11f,1980 thi l 14f&n l'
Oki/
Notary / ublic Ny Cocsission Expires V $ 7,
'/ '/
Enclosurc 8009050 $ 7 An equai opportunity cmpiover
ENCLOSURE SEQUOYAH NUCLEAR PLANT UNIT 1 STATUS OF LICENSING ITEMS REQUIRING RESOLUTION BEFORE EXCEEDING 5 PERCENT POWER OPERATION ITEM STATUS TVA shall station an operator in This requirement has been the control room with no other incorporated in the emergency duties than to monitor RHR system procedures.
performance when the RHR pumps are operating in the recirculation mode (SER section 6.3.3).
TVA must complete revisions to The procedures are under final plant procedures required as review (PORC). The procedures resolution to IE Bulletin 79-27 will have final approval by (SER section 7.10).
September 5, 1980.
TVA shall replace or qualify the The unqualified switches have unqualified switches (PDIS 1-17 been replaced with qualified and -16) located in steam valve switches.
room (SER sectin 7.2.2).
TVA is required to augment the TVA will have experienced control room staff for operation contractor employees available above 5 percent power through the to fulfill this requirement.
startup program up to and including 50 percent power operation.
l' TVA must satisfy the control room TVA has satisfied this background noise level criteria in requirement.
SER section 22.2.
i TVA is required to have an onsite TVA has employees available and Safety Engineering Group (SEG) (SER is organizing the group. The SEG section 22.2).
will be implemented before exceeding 5 percent power.
TVA is required to establish a TVA has met the full power near-site Emergency Operations requirements for an EOF as Facility (EOF) at the TVA Training described in NUREG-0694.
Center (SER section 22.2).
TVA will complete auxiliary The pump endurance test will be feedwater pump endurance tests and completed before exceeding 5 submit a report within 30 days of percent power. TVA will submit the completion of the test.
the report within 30 days of that date.
.TVA will incorporate new provisions TVA has satisfied this into the Secondary Water Chemistry requirement.
Program (SER section 5 3 2).
~