ML19338B949

From kanterella
Jump to navigation Jump to search
Forwards QA Program Insp Rept 99900004/80-01 on 800107-11 & Notice of Deviation
ML19338B949
Person / Time
Issue date: 01/22/1980
From: Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Richard C
GENERAL ATOMICS (FORMERLY GA TECHNOLOGIES, INC./GENER
Shared Package
ML19338B950 List:
References
REF-QA-99900004 NUDOCS 8004040348
Download: ML19338B949 (2)


Text

i

/

~

g-

- s UNITED STATES o u%c%,

NUCLEAR REGULATORY COMMISSION fi REGloN IV I

c-611 RY AN PLAZA DRIVE. SUITE 1000 t

art.!NGToN, TEXAS 76012

)

7 C'

sl

.N..

2 2 JAN 1ceo Dockat No.- 99900004/80-01 General Atomic Company EAttn:

Mr. C. L. Richard Executive Vice President

. Post Office Box 81608 San Diego, California 92138 Gentlemen:

This refers to the QA Program inspection conducted by Mr. W. M. McNeill of this office on January 7-11, 1980, of your facility at San Diego, California, associated with the manufacture and fabrication of nuclear fuel assemblies and to the discussions of our findings with Mr. T. R. Colandrea and members of your staff at the conclusion of the inspection.

This inspection was made to confirm that, in the areas inspected, your QA Program is being effectively implemented.

The inspection effort is not designed to assure that unique quality requirements imposed by a customer are being

-implemented; nor to assure that a specific product, component or service provided by you to your customers, is'of acceptable quality. As you know, the NRC requires each of its licensees-to assume full responsibility for the quality of specific products, cor.pocents or services procured from others.

You should therefore not conclude cnat the NRC's inspection exempts you from inspections'by an NRC licensee or his agents nor from taking effective cor-rective action in response to their findings.

Areas examined and our findings are discussed in the enclosed report.

Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and observations by the inspector.

During the inspection it was found that the implementation of your QA Program failed to meet certain NRC requirements.

The specific findings and references to the pertinent requirements are identified in the enclosures to this letter.

Please provide us within thirty (30) days of your receipt of this report a written statement containing, (1) a description of steps that have been or will

.be taken to correct these items, (2) a description of steps that have been or

.will be taken to prevent recurrence, and (3) the date your corrective actions and preventive measures were or will be completed.

N 800404o',3Lfg

General Atomic. Company.In accordance with Section 2.790 of the Commission's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this-letter with enclosure and your reply, together with ths, enclosed inspection report vill be placed in the Commission's Public Document Room.

If this report contains any.

information that you believe to be proprietary, 'it is necessary that you make a written application within thirty (30) days to this office to withhold such

~

information from public disclosure.

Any such application must. include a full statement of the reasons on the basis of which it is claimed that the informa-tion is proprietary, and should be prepared so that proprietary information identified in the application is contained in a separate part of the document.

If _we' do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.

Should you have any. questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, LL6LYkuw Uldis Potapovs, Chief.

Vendor Inspection Branch

Enclosures:

1.

Notice of Deviation 2.

Inspection Report No. 99900004/80-01 i