_ - _ _ _ _ -____ -

Of S-o f

Metropolitan Edison Company M

Post Office Box 480 Middletown, Pennsylvania 17057 717 9444041 Wnter's Direct Diat Number September 2, 1980 TLL 300 Office of Inspection and Enforcement Attn:

B. H. Grier, Director Region i U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pa.

19406

Dear Sir:

Three Mile Island Nuclear Station, Unit 1 (TMI-l' Operating License No. DPR-50 Docket No. 50-289 IE Bulletin 80-10 Attached please find our response to IE Bulletin 80-10 concerning the contam-ination of nonradioactive systems and the resulting potential for unmonitored, uncontrolled releases to the environment. A verification letter of completion of the corrective action will be forwarded per your request.

Sincerely, e

T J. G. Herbein

^

Vice President TMI-l JGH:DGM: hah Attachment cc:

R. W. Reid J. T. Collins B. J. Snyder D. DiIanni H. Silver 8 010 010M Q

YetrecoL:an Ed son Comrar.y ss a Memter of the Genera: PutSc UtQ:es System

I TLL 300 RESPONSE TO IE EULLETIN 80-10 A review of the facility design, including operational practices, was performed to identify systems that we considered to be nonradioactive but could possibly become radioactive through interfaces with radioactive systems.

This review gave special consideration to the following systems: Auxiliary Boiler System, Demineralized Water System, Condenser Vacuum System, Service Air System, Condensate Polishing Filter Unit System (Powdex System), Instrument Air System, and the Sanitary Waste System.

Procedure changes due to this review have been implemented.

A review of the Unit 1 Routine Sampling / Analysis Program resulted in an additional sampling requirement.

The' procedural changes have been implemented.

The requirements of items 3 and 4 of IE Bulletin 80-10 will be delinated in the appropriate sampling procedures.

In addition, guidance will be implemented detailing the administrative controls to be initiated with respect to the requirements of items 3 and 4 of IE Bulletin 80-10.

The above requirments are expected to be completed by September 22, 1980.

The details and specifics of the above stated reviews and subsequent procedure changes will be available for your on-site review.