Responds to IE Bulletin 80-19, Failure of 76 of 185 Control Rods to Fully Insert During Scram at Bwr. Util Has Ordered Scram Discharge Header Water Level Monitoring Sys
ML19337A151
Person / Time
Site: Pilgrim
Issue date: 08/14/1980
From: Andognini G, Andognni G
BOSTON EDISON CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
80-189, IEB-80-19, NUDOCS 8009090034
Download: ML19337A151 (1)


Text

Y%

BOSTON EDISON COMPANY

. GENEeAL Dmcts BOD RovisfoN SinECT Boston. MassacNusETTs 0219 9 August 14, 1980

a. c.=L ANoosmN.

sWPERINTENDENT -

RCLEAR OPERAftoNs OEPARTMENT BECo.'Ltr. #80-189 Mr. Boyce H. Grier, Directcr -

Office of Inspection and Enforcement Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA.

19406 License No. DPR-35 Docket No. 50-293

. Scram Discharge Volume Continuous Water Level Monitoring

References:

(a)

IE Supplement No. I to Bulletin 80-17 (b) GE Meeting between GE and NRC on August 6,1980 (c) GE Letter R.F. Thibault to BECo dated August 8, 1980 (d)

BECo response to IE Supplement No. 1 to Bulletin 80-17

^

Dear Mr. Crier:

In reference (a) Boston Edison Company was requested to either install a system to continuously monitor water 1cvels in the scram discharge volumes by September 1, 1980 or submit justification why the installation date cannot be met.

Boston Edison Company has ordered a Scram Discharge Header Water Level Monitoring System from General Electric Co. as discussed during reference (b).

Due.to the generic nature of this system and given that other utilities will re-quire the~same hardware at the same time it is anticipated that the earliest delivery date would be October 1, 1980. GE will advise us whmn the actual hard-ware delivery date is ascertained.

Upon receipt of this system we shall endeaver to install the equipment on a schedule which is both expeditious.

and practicable.

In the interim until sys-tem installation is complete, we shall continue the daily water level monitoring surveillance as specified in reference (d).

Should.you have an'; further questions or comments concerning this issue, please do not hesitate '.o contact us..

Very truly yours,

/

.<. l ! h,'/r. /

'J

/

cc:- Director.

Division of Reactor. Operations Inspection EU.S.' Nuclear Regulatory Commission Office of-Inspection and Enforcement Washington, D. C.

20555-

"144dw.

4 L

8009090034

~'

Notary Public f

,