Responds to Item B.1 of Bulletin 80-17,Suppl 1, Failure of 76 of 185 Control Rods to Fully Insert During Scram at Bwr. Facility Will Complete Installation of Continuous Monitoring Sys Before 801201
ML19336A211
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/16/1980
From: Pasternak R
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-80-17, JAFP-80-728, NUDOCS 8010220027
Download: ML19336A211 (2)


Text

.p+

IN POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITzPATRICK NUCLEAR POWER PLANT S

RAYMOND J. PASTERNAK P.O. Box 41 ResWent Maneger Lycommg. New York 13093 315-342-3840

~

September 16, 1980 SERIAL: JAFP 80-728 Boyce H. Grier, Director Nuclear Regulatory Comission Region I 631 Park Avenue i

King of Prussia, PA.

19406

SUBJECT:

NRC BULLETIN 80-17, SUPPLEMENT 1 ITEM B.1

Dear Mr. Grier:

Based on a NRC request for additional verbal and written comitments relating to the installation of a continuous monitoring J

system for the scram discharge volume, the coments below were pro-vided verbally on September 12, 1980 and are now provided in written j

form.

1)

The FitzPatrick Plant is comittij to make every attempt to complete installation of the continuous monitoring system on or before December 1, 1980.

2)

In consideration of our effort to meet this comitment, it should be noted that the FitzPatrick Plant has received the software transmittal associated with the continuous monitoring system.

Receipt of this transmittal will enable engineering of the power supply, inter-connecting cables, junction boxes and similar components to proceed.

3)

An engineering task to complete the necessary work noted in item 2) above has been initiated.

4)

The scheduled shipment date for the hardware is November 7, 1980.

The FitzPatrick Plant will attempt to improve this shipping date.

Significant deviation from the planned shipping date, which could result in a delay in installation beyond December 1, will be noted and the Comission will be notified as soon as practicable.

8010220 Q2 r/

Boyce H. Grier, Director September 16, 1980 Nuclear Regulatory Commission JAFP 80-728

SUBJECT:

NRC BULLETIN 80-17, SUPPLEMENT 1-Page i 5)

The continuous monitoring system which will be installed i

includes indication and alarm in the control room.

6)

Commencing at 0001 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Friday, September 12, ultrasonic surveillance of the scram discharge volume and associated l

piping was commenced once per shift with no less than six hours between the surveillance checks.

This surveillance i

shall be continued until installation of the continuous monitoring system is completed.

Very truly yours, f

l0(.by>wl l' duM~ ',

l RJP:brp RAYM0ND J. PASTERNAK CC:

George T. Berry, PASNY, NY0 J. P. Bayne, PASNY, NY0 G. M. Wilverding, PASNY, NY0 t

R. Baker, PASNY, JAF M. C. Cosgrove, PASNY, JAF NRCB 80-17 File Resident NRC Inspector l

Document Control Center 1

l L

l i

I l

l I

i

)

t