Northern Indiana Public Service Compang
~"
General Offces l 5265 H# man Avenue l Hammond. Inchana 46325 l Tel.: 853-5200 (219)
EUGENE M. SHoRS August 14, 1980 m r v.cc aacsiorm Mr. James G. Keppler, Regional Director U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE:
Docket No. 50-367 IE Bulletin 79-03A, " Longitudinal Weld Defects in ASME SA-312, Type 304 Stainless Steel Pipe"
Dear Mr. Keppler:
This is in response to NRC IE Bulletin 79-03A dated April 4,1980.
Northern Indiana Public Service Company's (NIPSCO's) Bailly Gen-erating Station Nuclear 1 (BGSN-1) construction is less than one per l
cent complete. There has been no piping installed. Construction as well as engineering on BGSN-1 has been halted for nearly three (3) years awaiting completion of NRC review of the BGSN-1 pile founda-tion. Accordingly, NIPSCO cannot make determination at this time as to whether SA-312 or A-312 Type 300 Series fusion welded pipe is planned to be used in the BGSN-1 facility.
NIPSCO will respond to this Bulletin as soon as practicable following l
resumption of engineering and construction on BGSN-1, or by January 4,1982.
Very truly yours, v -
EMS: cgs cc: U. S. Nuclear Regulatory Commission Office of Inspection & Enforcement Division of Reactor Construction Inspection Washington, D. C.