Responds to Requesting Fuel Load & Commercial Operating Schedule.Dates Unchanged Pending Schedule Review. Accurate Forecast Projected by Oct 1980
ML19331C800
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 08/12/1980
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
KMLNRC-020, KMLNRC-20, NUDOCS 8008190564
Download: ML19331C800 (1)


Text

KANSAS GAS AND ELECTRIC COMPANY GLENN L. aOCstte v Cg peasiogge.gg Nuclear August 12, 1980 Mr. Darrell G. Eisenhut, Director Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 KMLNRC-020 Re: Docket No. 50-482 Ref: Letter of 7/11/80 frem NRC to Applicants for Operating Licenses and Construction Permit Holders

Dear Sir:

Your letter of July 11, 1980, which we received July 21, requested an up-to-date sihedule of the Wolf Creek Generating Station Unit #1 fuel load and commercial operating dates.

l As of this time our dates are still October 1982 for fuel load, and April 1983 for commercial operation. We are, however, in the process of reviewing these schedules and should have a more accurate forecast by early October.

i I also understand that a tentative date of October 7 has been set for the Caseload Forecast Panel to visit Wolf Creek. We are quite confident

(

that we would be able to give the panel our best estimate of fuel load and commercial operation dates at that time.

If you need additional information concerning this issue, please advise me.