Submits Response to IE Bulletin 80-08 Re Containment Liner Penetration Welds.Deficiencies Found Will Be Radiographed During Aug 1980 Outage
ML19330C247
Person / Time
Site: Prairie Island  
Issue date: 07/22/1980
From: Gilberts D
NORTHERN STATES POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
IEB-80-08, IEB-80-8, NUDOCS 8008080134
Download: ML19330C247 (1)


Text

NSF NOMTHERN 3TATES POWER COMPANY MINN E APOLIS, MINN E SOTA 55401 July 22, 1980 Mr. James G. Keppler Dir2ctor, Region III Office of Irspection and Enforcement U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Dear Mr. Keppler:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 and 50-306 In further response to IE Bulletin No. 80-08, the following is offered:

Review of penetration welds has been completed for both units. As stated in our response of July 10, 1980, two welds in Unit I had inspection deficiencies.

These welds will be radiographed at the refueling outage scheduled for August 1980. No deficiencies were found in penetration welds in Unit 2.

Yours truly, D. E. Gilberts Vice President Power Production ec:

Mr. G. Charnoff Director, Division of Reactor Construction Inspection U. S. Nuclear Regulatory Commission Washington, D. C.

20555 DEG:nk muC 0 #

.Jou8080139