/" 'N Commonwealth Edison
)
- - One First National Plaza. Chic go flhnors 2
\\
/' Addr?.ss R: ply to: Post Office Box 767 3
Chicago, Illinois 60690 July 28, 1980 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555
Subject:
Zion Station Units 1 and 2 Status of Implementation of Elapsed Time Meters on Filter Systems NRC Docket Nos. 50-295 and 50-304 Reference (a):
April 28, 1980 letter from D. L. Peoples to H. R. Denton
Dear Mr. Denton:
Per Reference (a), Commonwealth Edison Company committeo to providing the NRC Stafi a status of the effort to install elapsed time meters for the various filter systems.
The meters are necessary to fully implement the proposed Technical Specifications contained in Reference (a).
Currently, the elapsed time meters and other equipment necessary to implement the meters have been procured.
The installation of the meters is on schedule and will be completed by September 1, 1980.
One (1) signed original and thirty-nine (39) copies of this letter are provided for your use.
Very truly yours,
(
j+ N '
W. F. Naugh Nuclear Licensing Administrator Pressurized Water Reactors 5602A 80080400 6g g