s LE(* A L oEPACTMINT Lavnenes S Landemar Vsce V.ess.seet and Genewal Ceonsel Judd L Secon Allen 8 Sa.a O < 9etersen Williarm E Wisner Manag'eg Atto reys Robert J Byen General offices; 212 West M6cMoon Avenwe, Jackson, MicNgan 49201 *(517) 788 0550 Howard a cserii Sesonov f Hagen Sewsoe 4t:3.neys July 22, 1980
,,,,,,,,x,,,,,,,,,,,,
J E 8,vaner c
g.u.aaum.
Lamov osoud o,-
o o-a..ne. W o.
v
. w.. p.. 3. 5...4..D..~..
i*:"n',*o*:,"
,,c
[...
g c
,L Ha.nes Richare H.-
l -n.-
nea.n L Jarean Won.4 x.,=.,
j.~......'.....
v.s,.n c u,un i~'..
Albert a McC.Jiuen lg o h M....n.
.-v r w. H Mm.
Mr. William O. Miller l,,,3.,..,q~,,..
l via= =
- re.- n.
_ _{
o"",,,"*n,
Chief, License Fee Management Branch
!"-~
Office of Admiaistratien
,C'**'v ^ S'ad' U.S. Nuclear Regulatory Commission nei. escorts..r.
Washington, DC 20555 O,'J yo,,,
Alter'reys Re: Docket Nos. 50-329, 50-330
Dear Mr. Miller:
Your letter dated July 3,1980, to Mr. Judd Bacon vas referred to me for research and response. You will recall that your letter set forth the reasons for the staf f judgment that Consumers Power Company should submit a fee with its December 19, 1979, Application for Construction Permit Amend-ments.
Af ter careful consideration and reflection, I am unable to e'ndorse your argu-ment for excluding the proposed amendments from the rule in footnote 2 to 10 CFR 170.22, which excepts such amendments frem the license fee requirements.
While it is true that the December 6, 1979, order does not specifically order Consumers to submit amendments to its CP, there is nothing in footnote 2 which requires that the Commission have ordered the permitee to submit an amendment.
The language in footnote 2 states that the amendments must have "resulted di-rectly from" 2.2')4 orders, not that the amendments themselves must be " ordered" pursuant to 2.204 If your argument were correct, then the Cocmissica could in all cases avoia the impact of its own rules by structuring its 2.204 order so as to avoid directly requiring the licensee to submit amendments, while putting the licensee in a position where its choice is either to submit amend-ments or to shut down its project.
Such an order has both the practical and the legal effect of requiring the submission of amendments. Further, your interpretation would give the Co= mission unbridled discretion to choose among permitees subj ect to 2.204 orders for purposes of charging application fees, by a simple choice as to the technical wording
' its order under 2.204.
Such discretion is permitted by neither the APA nor the Dua. Process Clause.
gO
%s 800729070l
William O. Miller NRC (Docket Nos. 50-329, 50-330)
July 22, 1980 2
Notwithstanding the above, requiring application fees in this case would subvert the NRC's own policies, as set forth in footnote 2 of 10 CFR 170.22 and in 42 FR 22156 (5/2/77), Item 6, which was referred to in Mr. Bacon's letter of April 3, 1980. These policies apply regardless of the technical wording of the order or of the technical structuring of the order-a=endment sequence.
Since the litmus test for re. ulatory construction is the purpose for which the regulation was promulgated, policy considerations rather than semantics should be controlling.
Your letter also states a more substantive argument for requiring payment of amendment fees, based on the fact that Consumers had undertaken remedial action on its soils problems.
It is unclear to us how the policies referred to above are furthered by requiring license fees from those who voluntarily choose to take remedial action and not from those who wait until ordered to do so pursuant to a 2.204 amendment.
Such is the clear implication of your argument. Also, neither the individual interests of the NRC nor the health and safety of th< public are adversely af fected by voluntary remedial action conducted in full sunshine.
In meetings related to the soils question the staff led Consumers to believe that it could undertake remedial action, at its own risk, and provide simul-taneous assurances through 50.54f responses. The following from the mirutes of aa October 16, 1979, meeting documenta that staff posture:
"The staff noted that the response to its 10 CFR 50.54 requests for acceptance criteria for remedial actions (e.g. questions 4,6, etc., ) had not resulted in identi-fication of criteria in advance of remedial action.
Rather, the reply notes that the criteria will be deter-mined during or aJter remedial action. The staff stated that this approach by the applicant does not provide for timely staff feedback at the outset, but rather the staff must await results of the program to determine what acceptance criteria were used and if they are acceptable. Thus, remedial action is being conducted entirely at the applicant's own risk."
(Summary of July 18, 1979, meeting on soils deficiencies at the Midland Plant Site, October 16, 1979, at p?;S 2, published by_NRC.)
l i
I i
William O. Miller NRC (Docket Nos. 50-329, 50-330)
July 22, 1980 3
At some point the segff became dissatisfied with this approach, which led to its issuance of the December order.
However, the change in staff pos-ture put Consumers in the position of having undertaken remedial steps prior to the issuance of the 2.204 order. To now charge a license fee on that basis seems, at the very least, unfair.
For the reasons noted above, we again respectfully request that you reconsider your position on this issue. Thank you for your cooperation.
Very truly yours, James E. Brunner CC: JLBacon, M-1085A MMiller, (I,L, & B)
TJSullivan, P-24-624 JWCook, P-14-113 GSKeeley, P-14-408B SEHowell, P-26-336B I