Responds to NRC Re Violation Noted in IE Insp Rept 50-306/78-24.Corrective Actions:Replacement of Snubbers Planned for Refueling Shutdowns,Unless Earlier Cold Shutdown Occurs
ML19330A367
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 05/23/1980
From: Gilberts D
NORTHERN STATES POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19330A363 List:
References
NUDOCS 8007170194
Download: ML19330A367 (1)


Text

-

~.

r.. gy

  • O NSP NORTNERN STATES POWER COMPANY wi= ~ samou s. usu u s sora se o,

May 23,1980 Mr. James G. Keppler Director, Region III Office of Inspection and Enforcement U. S. Nuclear Regulatory Cec: mission 799 Roosevelt Road Glen Ellyn, IL 60137

Dear Mr. Keppler:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket No. 50-306 Inspection Report 50-306/78-24 In further response to your letter of January 23, 1979, which transmitted Inspection Report 50-306/78-24, the following is offered.

In our response of December 13, 1979, we anticipated replacement of Anker Material de-Holth snubbers by May 1980 if material delivery was complete.

livery is not complete but is expected to be shortly.

However, analysis of the work procedures for these replace =ents has led to the conclusion that the work should not be done with the units above cold shutdown. Accordingly, thc repiccements are now planned for refueling shut-downs (August 1980 for Unit 1, January 1981 for Unit 2) unless an earlier cold shutdown of sufficient length takes place.

Yours truly,

/

(, try D. E. Gi'.berts Vice President Power Production ec:

Mr. G. Charnoff DEG:nk 8007170194 g;;( 30 isso