October 23, 1974 i

UNITED STATES OF AMERICA ATOMIC ENERGY COMMISSION Before the Atemic Safety and Licensing Board In the Matter of

)

)

THE TOLEDO EDISON COMPANY and

)

THE CLEVELAND ELECTRIC ILLUMINATING

)

COMPANY

)

(Davis-Besse Nuclear Power Station,

)

Docket Nos. 50-34 A Unit 1)

)

50-440A

)

50-441A i

THE CLEVELAND ELECTRIC ILLUMINATING

)

l COMPANY, ET AL.,

)

l (Perry Nuclear Power Plant,

)

Units 1 and 2)

)

MOTION FOR EXTENSION OF TIME 1.

By Memorandum and Order dated August 12, 1974, the Licensing Board amended the Hearing Schedule set forth j

l in Prehearing Conference Order No. 2 to require the completion of all documentary discovery and responses to interrogatories by October 31, 1974.

Applicants hereby move for a 30-day extension of time, until November 30, 1974, wichin which to produce documents and answer interrogatories.

It is further requested that the remaining dates in the Hearing Schedule be adjusted to reflect a similar extension.

2.

This motion for more time is necessary to provide Applicants a reasonable opportunity to inspect all relevant files since September 1, 1965 -- which is alone a monumental task -- and remove therefrom the various documents which nust 80 0 2180 gg-

_~

. be produced.

Applicants did not receive the Licensing Board's October 11 " Order On Objections To Interrogatories And Docu-ment Requests" until Oct'ober 15, 1974 At that particular time, counsel for Applicants were totally preoccupied with other matters, including the preparation of an extensive Reply Memorandum relating to Applicants' Motion for Summary Dispo-sition, which was filed with the Licensing Board on October 21, 1974.

Accordingly, Applicants' counsel are only now in a po-sition to begin coordinating the time-consuming file searches that must be undertaken in compliance with the documentary discovery requests.

From a preliminary examination of the volume of material involved, the additional 30 days are abso-lutely essential to permit the Applicants to make the thorough file inspection required by the Licensing Scard's Order in order to assure a proper and complete document production.

3.

Counsel for the City of Cleveland has authorized Applicants' undersigned counsel to state that the City joins in this request for more time.

Both the Department of Justice and the AEC Regulatory Staff have advised that they do not oppose the motion.

Respectfully submitted, SHAW, PITTMAN, POTTS & TROW 3 RIDGE By 9._. -N.. N _.. A

._. _ A Wm. Bradford Reynolds Gerald Charnoff Counsel for Applicants Dated:

October 23, 1974

~

UNITED STATES OF AMERICA ATOMIC ENERGY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of

)

)

THE TOLEDO EDISON COMPANY and

)

THE CLEVELAND ELECTRIC ILLUMINATING

)

COMPANY

)

(Davis-Besse Nuclear Power Station,

)

Docket Nos. 50-346A Unit 1)

)

50-440A

)

50-441A THE CLEVELAND ELECTRIC ILLUMINATING

)

COMPANY, ET AL.,

)

(Perry Nuclear Power Plant,

)

Units 1 and 2)

)

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing

" Motion For Extension Of Time" were served upon each of the persons listed on the attached Service List by U. S.

Mail, postage prepaid, on this 23rd day of October, 1974.

SHAW, PITTMAN, POTTS & TROWBRIDGE lb_ _.c /

By (D

~L

\\

Wh. Bradford Reynoldst Counsel for Applicants Dated:

October 23, 1974.

_-.~

e

?

1 UNITED STATES OF AMERICA ATOMIC ENERGY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of

)

)

THE TOLEDO EDISON COMPANY and

)

THE CLEVELAND ELECTRIC

)

ILLUMINATING COMPANY

)

)

(Davis-Besse Nuclear Power

)

Docket Nos. 50-346A r

Station, Unit 1)

)

50-440A

)

50-441A THE CLEVELAND ELECTRIC

)

ILLUMINATING COMPANY, ET AL. )

)

(Perry Nuclear Power Plant,

)

Units 1 and 2)

)

SERVICE LIST John B. Farmakides, Esq.

Mr. Chase R. Stephens Chairman Docketing & Service Section Atomic Safety and Licensing Board U. S. Atomic Energy Ccmmission U. S. Attmic Energy Commicsion 1717 H Street, N.W.

Washington, D. C. 20545 Washington, D. C.

20545 John H. Brebbia, Esq.

Benj amin H. Vogler, Esq.

Atomic Safety and Licensing Board Office of General Counsel Alston, Miller & Gaines Regulation i

1776 K Street, N.W.

U. S. Atomic Energy Commission Washington, D. C. 20006 Washington, D. C.

20545 f

Douglas V. Rigler, Esq.

Robert J. Verdisco, Esq.

Atomic Safety and Licensing Board Office of General Counsel i

Foley, Lardner, Hollabaugh Regulation l

and Jacobs U. S. Atomic Energy Commission Schanin Building Washington, D. C. 20545 815 Connecticut Avenue, N.W.

1 i

Washington, D. C. 20006 Andrew F. Popper, Esq.

l Office of General Counsel

)

l Atomic Safety and Licencing Regulation i

l Board Panel U. S. Atomic Energy Commission U. S. Atomic Energy Commission Washington, D. C.

20545 Washington, D. C.-20545 l

l

m o Joseph J. Saunders, Esq.

Leslie Henry, Esq.

~~

Steven Charno, Esq.

Fuller, Henry, Hodge & Snyder Antitrust Division 300 Madison Avenue Department of Justice

~ Toledo, Ohio 43604 Washington, D. C. 20530 Thomas A. Kayuha, Esq.

Melvin G. Berger, Esq.

Ohio Edison Company Antitrust Division 47 North Main Street Department of Justice Akron, Ohio 44308 Washington, D. C. 20530 Thomas J. Munsch, Esq.

Reuben Goldberg, Esq.

General Attorney David C. Hj elmfelt, Esq.

Duquesne Light Company 1700 Pennsylvania Ave., N.W.

435 Sixth Avenue Washington, D. C. 20006 Pittsburgh, Pennsylvania 15219 Frank R. Clokey, Esq.

David Olds, Esq.

i Special Assistant Reed, Smith, Shaw & McClay Attorney General Union Trust Building Room 219 Box 2009 Towne House Apartments Pittsburgh, Pennsylvania 15230 Harrisburg, Pennsylvania 17105 John Lansdale, Esq.

Mr. Raymond Kudukis Cox, Langford & Brown Director of Utilities 21 Dupont Circle, N.W.

City of Cleveland Washington, D. C. 20036.

1201 Lakeside Avenue Cleveland, Ohio 44114 Wallace L. Duncan, Esq.

Jon T. Brown, Esq.

Herbert R. Whiting, Director Duncan, Brown & Palmer Robert D. Hart, Esq.

1700 Pennsylvania Ave., N.W.

Department of Law Washington, D. C.

20006 1201 Lakeside Avenue Cleveland, Ohio 44114 Dwight C.

Pettay, Jr.

Assistant Attorney General John C. Engle, President Chief, Antitrust Section AMP-0, Inc.

30 East Broad Street, 15th Floor Municipal Building Columbus, Ohio 43215 20 High Street Hamilton, Ohio 45012 Deborah Powell Highsmith, Esq.

Assistant Attorney General Donald H. Hauser, Esq.

Antitrust Section Managing Attorney 30 East Broad Street, 15th Floor The Cleveland Electric Columbus, Ohio 43215 Illuminating Company 55 Public Square Christopher R. Schraff, Esq.

Cleveland, Ohio 44101 Assistant Attorney General Environmental Law Section

-361 East Broad Street, 8th Floor Columbus, Ohio 43215