ML19329B985

From kanterella
Jump to navigation Jump to search
Notice of Issuance & Availability of Amend 14 to License NPF-3
ML19329B985
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/13/1979
From: Reid R
Office of Nuclear Reactor Regulation
To:
Shared Package
ML19329B960 List:
References
NUDOCS 8002110770
Download: ML19329B985 (2)


Text

_

~

7590-01 w

UNITED STATES NUCLEAR REGULATORY COMMISSION DOCKET NO. 50-346 THE TOLEDO EDISON COMPANY AND THE CLEVELAND ELECTRTC ILLUMINATING COMPANY NOTICE OF ISSUANCE OF AMENDMENT TO FACILITY CPERATING LICENSE 4

The U. S. Nuclear Regulatory Commission (the Comission) has issued Amendment:No.14 to Facility Operating License No. NPF-3, issued to The Toledo Edison Company and The Cleveland Electric Illuminating Company (the licensees), which revised the license for operation of the Davis-Besse Nuclear Power Station, Unit No.

.1 (the facility), located in Ottawa County, Ohio. The amendment is effective as of its date of issuance.

The amendment modifies the license to include the current Commission-approved physical security plan.

The licensees' filings comply with the standards and require-ments of the Atomic Energy Act of 1954, as amended (the Act), and the Comission's rules and regulations ~. The Comission has made appropriate findings as required by the Act and the Comission's rules and regulaticns in 10 CFR Chapter I, which are set forth in the license amendment.

Prior public notice of this amendment was not required since the amendment does not involve a significant hazards consideration.

R0021107N 4

7590-01 y

. The Comission has determined that the issuance of this amendment will not result in any significant environmental impact and that pursuant to 10 CFR 551.5(d)(4) an environmental impact statement or negative declaration and environmental impact appraisal need not be prepared in connection with issuance of this amendment.

The licensees' filing dated June 5,1978, revised September 20, 1978, November 10, 1978, December 26, 1978, January 12, 1979, February 22, 1979 and March 10, 1979, and the Comission's Security Plan Evaluation Report are being withheld from public disclosure pursuant to 10 CFR 2.790(d). The withheld information is subject to disclosure in accordance with the provisions of 10 CFR 19.12.

For further details with respect to this action, see (1)

Amendment No.14 to License No. NPF-3 and (2) the Comission's related letter to the licensee dated April 13, 1979.

These items are available for public inspection at the Comission's Public Document Room,1717 H Street, N.W., Washington, D.C. and at the Ida Rupp Public Library, 310 Madison Street, Port Clinton, Ohio.

A copy of items (1) and (2) may be obtained upon request addressed to the U. S. Nuclear Regulatory Comission, Washington, D.C.

20555, Attention: Director, Division of Operating Reactors.

l Dated at Bethesda, Maryland, this 13th day of April 1979.

FOR THE NUCLEAR REGULATORY COMMISSION h

Y.

Robert W. Reid, Chief Operating Reactors Branch #4 Division of Operating Reactors

,