Responds to Generic Ltr 89-16, Hardened Vent, by Encouraging Licensees to Voluntarily Install Hardened Vent Under 10CFR50.59
ML19327B615
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 10/24/1989
From: Hairston W
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-89-16, HL-782, NUDOCS 8911020278
Download: ML19327B615 (2)


Text

,

l Geova Power Company -

f.

g<

333 Paedmore Aenue' Ananta. Googa 30300 Tetophone 404 626 3195 l

Mading Address 40 inverness Center Parkway 1

Post Office Box 1295 l

B.trningham Alabama 35201

.i Telephone 205 868 5501 4

r Inc.% wen ewnc systern W, G. Hairston.111 Senior %ce President l

Nuclear Operat;ons HL-782 0334V I

october 24, 1989 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Hashington, D.C.

20555-a PLANT HATCH - UNITS 1, 2 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES.DPR-57, NPF,

' GENERIC LETTER 89-16 HARDENED VENT l

Gentlemen:

On September 1, 1989, the NRC staff issued Generic LL'etter 89-16 to inform the-owners of BHR plants with Mark I containments of the NRC program for disposition of. the issues related to the Mark I Containment Performance Improvement Program.

This letter encouraged.' licensees to voluntarily install a hardened vent under 10 CFR 50.59.

Our review of SECY 89-017 indicates that the ' primary. benefit of the hardened vent is the reduction of risk associated with the TN (long term loss of decay heat ~ removal) sequence.

It is the intention of Georgia

{

Power Company to install a hardened vent to reducen the risk of the TH sequence at Plant E. I. Hatch, Units 1 and 2.

Georgia Power. Company will be working with the BHR Owners' Group to develop - generic general and specific design critoria.

It is anticipated that. the' design criteria will be available for NRC review by April 30, 1990.

Specific design-details will be available as Georgia Power Company completes the appropriate portions of the IPE for Plant Hatch and'. studies the l

possibility of systems' interaction effects-between the vent and the:

existing plant design.

The hardened ' vent will be. insta11ed' on: Unit 1 l

before startup from the end of. cycle.14 refueling outage and on Unit 2-i before startup from the end of cycle 10 refueling outage.

It is the belief of Georgia Power Company that; the risk.~of the'TH sequence is Ealready low.

The installation of 'the hardened vent: will further reduce risk of this sequence. and make a significant contribution'

'f to closing the NRC Mark.I Containment Performance Improvement Program.-

na Anocx osoooaar l

891102027s s92oa4 r PNU g i ;' 9

,f

.c

. ~..

i

' beorgia Power b U.S. Nuclear Regulatory Comission october 24, 1989 Page Two If you hwe any questions in this regard, please contact this office.

Sincerely, td./b. $"m H. G. Hairston, III JKB/eb c: Georaia Power ComDany Mr. H. C. Nix, General Manager - Puclear Plant Mr. J. D. Heidt Manager Engineering and Licensing - Hatch GO-NORMS U.S. Nuclesr Reaulatory Comission. Washinaton. 0.C.