ML19327A210

From kanterella
Jump to navigation Jump to search
Responds to IE Bulletin 79-03A, Longitudinal Weld Defects in ASME SA-312,Type 304 Stainless Steel Pipe. Safety-related Piping Sys Reviewed.No SA-312 or A-312 Welded Pipe in Use Greater than 85% of Code Allowable Stress
ML19327A210
Person / Time
Site: Haddam Neck, Millstone  File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 07/11/1980
From: Counsil W
CONNECTICUT YANKEE ATOMIC POWER CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
A00956, A956, IEB-79-03A, IEB-79-3A, NUDOCS 8008010280
Download: ML19327A210 (2)


Text

1A l

Pit)ft11HII!JL!rr III'llJrrIE!5 h*,

1 l

N ONNECTICUT 06101 "a

<L =====:

July 11, 1980 Docket Nos. 50-213 50-245 50-336 A00956 Mr. Boyce H. Grier, Director Region I Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406

Reference:

(1)

B. H. Grier letter to W. G. Counsil dated April 4,1980, transmitting I&E Bulletin No.79-03A.

Gentlemen:

Haddam Neck Plant Hillstone Nuclear Power Station, Unit Nos.1 and 2 I&E Bulletin No.79-03A In Reference (1), the NRC Staff requested that Connecticut Yankee Atomic Power Company (CYAPCO) and Northeast Nuclear Energy Company (NNECO) determine whether SA-312 or A-312, Type 300 Series fusion welded pipe is in use or planned for use in safety-related systems subject to design stresses greater than 85% of the Code Allowable stresses.

In response to Item 1 of Reference (1), CYAPCO and NNECO provide the following information for the Haddam Neck Plant and Millstone Unit Nos.1 and 2.

Haddam Neck Plant CYAPCO has reviewed the safety-related piping systems at the Haddam Neck Plant and has determined that there is no SA-312 or A-312 welded pipe in use at greater than 85% of the Code Allowable stress.

008010 @

8

. Millstone Unit No. 1 NNECO has reviewed the piping systems at Millstone Unit No. 1 and has determined that there is no welded SA-312 or A-312 pipe in use at Millstone Unit No. 1.

Millstone Unit No. 2 NNECO has reviewed the safety-related piping systems at Millstone Unit No. 2 and has determined that there is no SA-312 or A-312 welded pipe in use at l

greater than 85% of the Code Allowable stress.

As there is no SA-312 or A-312 welded pipe subject to design stresses greater

- than 85% of the Code Allowable stresses at the Haddam Neck Plant, Millstone Unit No.1, or Millstone Unit No. 2, Item 2 of Reference (1) is not applicable.

We trust you find this information satisfactorily dispositions the Reference (1) concerns. No further action is planned.

Very truly yours, CONNECTICUT YANKEE ATOMIC POWER COMPANY NORTHEAST NUCLEAR ENERGY COMPANY A//N0L W.' O. Counsil Senior Vice President r