| Issue date: | 06/05/1980 |
| From: | Potapovs U NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Derienzo P GIBBS & HILL, INC. (SUBS. OF DRAVO CORP.) |
| Shared Package | |
| ML19327A068 | List: |
| References | |
| REF-QA-99900524 NUDOCS 8008010123 | |
| Download: ML19327A070 (1) | |
Text
_
p 0
UNITED STATES
~3
- 4
/
9'o, NUCLEAR REGULATORY COMMISSION REGION IV J 'I i /[* 4 1
2 611 RY AN PLAZA ORIVE. SulTE 1000 I
- 7. -
'%,'s /
0 5 JUN 1980 X
Occket No.
99900524/80-01 Gibbs and Hill, Incorporated Attn: Mr. Paul P. DeRien::o Vice President Quality Assurance 393 Seventh Avenue New York, NY 1C001 Gentlemen:
Thank you for your letter of April 25, 1980, in response to our letter dated March 29, 1980. As a result of our review, we find that addi-tional infonnation, as discussed with you and Mr. N. N. Xeddis during a telephone call on May 28, 1980, is needed.
With respect to deviation A, please identify the method (s) and date(s) by which Gibbs and Hill will detennine that all of the requirements of ANSI N 45.2.12 are included in procedures QA-2, QA-4, and QAI-7 as apprcpriate.
4 With respect to deviation B, please indicate whether procedure QAI-l will require revision to reflect the new system for control of manuals and if so describe the nature of the revision and the date it will be acccmplished.
With respect to corrective actions concerning deviation C, please describe the cause contributing to this deviation, if the deviation relative to spec No. MS-43A was an isolated case (and your bases), and hcw you have assurance that other specifications do not have similar deviations.
Please provide this additional infonnation within twenty (20) days in order that we may ccmplete our review in a timely manner.
Sincerely,
\\
C at Uldis'. tapovs, Chief Vendor Inspection Br nch j