ML19326E079

From kanterella
Jump to navigation Jump to search
Qa Program Insp Rept 99900398/80-01 on 800505-09. Noncompliance Noted:Practices Not Consistent W/Criterion 5, App B to 10CFR50 & Section 1.4,Issue a of Product Design Engineering Manual
ML19326E079
Person / Time
Issue date: 05/20/1980
From: Bennett A, Foster W, Hunnicutt D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19326E075 List:
References
REF-QA-99900398 99900398-80-1, NUDOCS 8007250594
Download: ML19326E079 (9)


Text

-

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT REGION IV Report No. 99900398/80-01 Program No. 51400 Company:

General Electric Company Wire and Cable Business Department 1285 Boston Avenue Bridgeport, Connecticut 06602 Inspection Conducted: May 5-9, 1980 Inspector':

  • h/

c,. uc M 2O "C>

  1. W. E. F6 ster, Contractor Inspector Date ComponentsSection II Vendor Inspection Branch hY _ Ywmees2 6Y: C/EO Observer:

/!

A. B. Bennett, Senior Electrical Engineer

' Dats f.,

Division of Reactor Construction Inspection Approved by:

0 b/ Mt.-iz,ez#

3 J C /.PO D. M. Hunnicutt, Chief Date' ComponentsSection II Vendor Inspection Branch Summary:

Inspection on May 5-9, 1980 (99900398/80-01).

Areas Inspected:

Implementation of 10 CFR 50, Appendix B criteria, and appli-cable codes and standards; including follow-up on inspector iuentified unresolved item; manufacturing process control; and change control.

The inspection involved forty-four and one-half inspector-hours on site by two NRC inspectors.

Results:

In the three areas inspected, no unresolved items were identified; the following three deviations were identified:

Deviations: Manufacturing Process Control practices were not consistent with Criterion V of Appendix B to 10 CFR 50; paragraphs 1.1, 1.3.3, and 2.11.6.1 of Section 1.4, Issue A, dated March 7, 1966, e' the Product Design Engineering Manual (See Notice of Deviation, Item A); and Bridgeport Manufacturing Instruc-tions No. 8, Section 2, dated October 8, 1975 (See Notice of Deviation, Item B).

8007250594;

2 i

Change Control - practices were not consistent with Criterion V of Appendix B to f?

10 CFR 50; and paragraph 2.1 of Section 1.9, Issue A, dated October 19, 1964, of the Product Design Engineering Manual (See Notice of Deviation, Item C).

Unresolved Items: None.

.- _,,... _,., ~ -.

3 DETAILS SEC1 ION A.

Persons Contacted

  • A. C. Bruhin, Manager - Product Development
  • D. G. Connelly, Manager.- Quality Control
  • H. J. Cunha, Manager - Requisition and Specification Engineering
  • J. W. Fillmore, Manager - Bridgeport Cable Plant J. R. Galloway,. Manager - Industrial and Utility Sales
  • W. J. Gartin, General Manager
  • S. Hamilton, Manager - Engineering
  • C. Hayner, Manager - Manufacturing R. Hopkins, Engineer - Quality Control, Wire Mill E. R. Kingsbury, Engineer - Product Development i

T. K. Kurien, Engineer - Quality Control, Compounding and Incoming Material M. Mosley, Engineer - Product Development and Test R. N. O'Donoghue, Engineer - Product Design

  • L. S.'Skorz2wski, Manager - Test and Quality Assurance
  • J. E. Sweeney, Engineer - Senior Quality Control
  • Attended Exit Interview.

B.

Follow-up on Inspector Identified Problems and Unresolved Items 1.

Objectives The objectives of this area of the inspection were to verify that inspector identified problams anc unresolved items, during previous inspections, had been corrected and resolved satisfactorily.

2.

Methods of Accomplishment The preceding objectives were accomplished by:

Reviewing General Electric Company, Wire and Cable Business a.

Department's (GECo WCBD) letters, dated April 21 and 29, 1980, to Bechtel Power Corporation;

Subject:

San Onofre Nuclear Generating Station Unit Nos. 2 and 3.

b.

Discussing acceptability /non-acceptability of splicing with cognizant personnel, Reviewing Bechtel Power Corporation's letter (Log BX-5777),

c.

dated April-22, 1980, to GECo WCBD;

Subject:

Southern California Edison Company San Onofre Nuclear Generating Station, Units 2 and 3 and its enclosure entitled - Supplier Deviation Disposition Request, Bechtel SDDR No. 2053 (GECo WCP7 No. 33) dated April 22, 1980.

wa 4

't 4

d.

Reviewing Franklin Research Center's Final Report No. F-C5285-1

.(PRELIMINARY);

Subject:

Qualification Tests of Electrical Cables in a simulated Loss-of-Coolant (LOCA) Environment.

Reviewing Franklin Research Centr.r's letter, dated February 27, l

e.

1980.tc GECo WCBD;

Subject:

Qualificatio. Testing of EP Neo-prene Electrical Cables, FRC Project C5285.

i f.

Reviewing GECo WCBD's Product Development Report No. PD-7-80, dated March 11, 1980, which addressed thermal tests of reworked conductors and insulation.

3.

Findings (Closed) Unresolved Item (Inspection Report No. 79-01):

The inspector verified that Note No. 8 of the Contingent Purchase Order Release had been modified to read:

" Single and/or multi-conductor cable lengths will not be joined to obtain shipping cable length requirements except in accordance with Bridgeport Manufacturing Instruction #13, Section 7-0."

4

-6her Related Findings The Franklin Research Center's letter of February 27, 1980, a.

indicated that two of the five specimen failed to maintain the electrical load during the 33-day exposure to the quali-fication test environment.

This failure is attributed to probable faulty vessel penetrations.

I b.

Power cable (600 volts) with vulkene supreme insulation will be supplied to Bechtel/ Southern California Edison Company for San Onofre Nuclear Generating Stations, Unit Nos. 2 and 3.

The change of insulation material is identified in Contingent Purchase Order Release No. 304-11-024 and Supplier Deviation Disposition Request (SDDR) No. 2053. Bechtel has approved the SDDR and_is scheduled to issue Memorandum of Change No. 19 to

-Purchase Order No. D4103051.

Qualification testing had been successfully accomplished on lengths of cable insulated with the

.vulkene supreme material. The test specimens were constructed with brazed joints and patched insulation.

C.

Manufacturing Process Control 1.

Objectives-

-The objectives of this area of the inspection were to verify that measures had been established and documented to control manufacturing, inspection and test activities. Also, to verify these activities had

5 een' accomplished in accordance with the established and documented measures. Additionally, verification of indication of mandatory hold points in appropriate documents.

2.

Methods of Accomplishment The preceding objectives were accomplished by:

4 Reviewing the following documents to verify measures had been a.

established and documented to control manufacturing, inspection and test activities:

(1) Wire and Cable Jusiness Department's Quality System Manual, Revision A, dated June 9, 1978; Sections 5.0; 8.0; 9.0; 10.0; 11.0; and 14.0.

(2) Product Design Engineering Manual, Section Nos. -

(a) 1.4, Issue A, dated March 7, 1966 - Product Design Specifications, (b) 1.4A, Issue A, dated February 22, 1977 - Product Design Specifications - New Products, and (c) 1.4B, Issue A, dated February 22, 1977 - Product Design Specifications - Requiring Traceability.

(3) Bridgeport Manufacturing Instructions, Nos. -

(a) 1, Section 8-0, dated March 21, 1980 - Clerical Procedr es and Foutines Inspection Status Routine, (b) 1, Section 16, dated March 21, 1980 - Clerical Procedures and Routines Inspection Plan Procedure.

(c) 6, Section 15, dated August 20, 1970 - Wire Drawing WF-14 Intermediate Wire Drawing Machine,

]

(d) 2, Section-78, dated June 21, 1967 - Operating Procedure for Quality Spark Test and Inspect Operations, (e) 2, Section 90, dated December 9, 1975 - Operating Procedure for Quality Electroplating Lines, 4

(f) 2, Section 98, dated October 30, 1975 - Operating Procedures for Quality Niehoff M-5 Wire Drawing

Machine,

a 1

6 (g)

-7, Section 4, dated February 20, 1975 - Annealing Bell Annealing - 0, (h) 8, Section 2, dated October 8, 1975 - Tinning Electro-

plating, (i) 25, Section 2, dated February 13, 1979 - Testing Pr sration of Cable Ends for Power Cable Rated up to 35 KV; (j) 25, Section 35, dated December 11, 1979 - Testing Insulation Resistance, (k) 25, Section 38C, dated February 11, 1980 - Testing Conductor Resistance, (1) 30, Section 16-0, dated August 23, 1965 - Quality Control Inspection Procedure (QCIP) Determination of Cross-Section Area of Stranded Conductors, (m) 30, Section 19-0, dated March 26, 1963 - QCIP Vulkene Cure Test, (n) 31, Section 12, dated July 14, 1970 - Quality Con-trol Laboratory Procedures for Sampling, Testing, and Releasing Vulkene Compound, and (o) 11, Section 81, sheet 11, dated August 23, 1979 -

Tubing Operating Instructions Compound 3067.

(4) Materials Analysir and Testing Procedure No. 010-A, dated December 5, 1969 - Determination of Cure with Monsanto Rheometer, and (5;

Temporary Standing Instruction No. T3067-25-01C, dated March 21, 1980.

b.

Observing the following activities to verify that tasks were being accomplished in accordance with established and documented measures: Engineering Control of Custom Order Product Design Specifications; 5' ire Drawing; Vire /nuealing (Bell); Wire Tinning; and Testing of Vulkene Supreme Compound.

3.

Findings a.

Deviations From Commitment l

l (1) See Notice of Deviation, Item A.

l i

r.

7 L(2) See Notice of Deviation, Item B.

b.

Unresolved Items None.

D.

Change Control 1.

Objectives The objectives of this area of the inspection were to verify that measures had been established to control changes to software and hardware.

Also, to verify the measures for software changes included provisions for review, approval, and distribution to and usage at the location where the prescribed activity is per-formed. An additional phase was to verify the measures had been implemented.

2.

Methods of Accomplishment The preceding objectives were accomplished by:

a.

Reviewing the following documents to verify measures had been established to control changes to software and hardware:

(1) Wire and Cable Business Department's Quality System Manual, Revision A, dated June 9, 1978; Sections 3.0; 6.0; and 15.0.

(2) Product Design Engineering Manual, Section Nos. -

1 (a) 1.4, Issue A, dated March 7, 1966 - Product Design Specifications, (b) 1.5, Issue A, dated January 5, 1965 - Product Design

File, (c) 1.9, Issue A, dated October 19, 1964 - Engineering Change Authorization, and (d) 1.10, Iss'te A, dated March 16, 1965 - Alteration Notice.

(3) Bridgeport Manufacturing Instructions Nos. -

t (a) 1, Section 5-0, dated March 24, 1980 - Clerical Procedures and Rortines Drawing and Change Control, l

l-1 l

1

8 (b) 20, Section 12, dated December 17, 1976 - Quality Control Procedures Quality System Manual Control, and (c) 1, Section 12, dated April 11, 1980 - Clerical Procedures and Routines Bridgeport Manufacturing Instrus.tions.

b.

Reviewing the changes.and attendant documentation on the follow-ing to verify that established measures had been implemented:

(1) Section 1.7, page 5, Issue D, dated April 27, 1970; Section 1.8, Issue D, dated May 11, 1970; Section 7.1, page 7, Issue B, dated April 30, 1973.

The sections are part of the Product Design Engineering Manual.

(2) Engineering Change Auth:rization Logs for 1970, 1973, and 1980.

3.

Findings a.

Deviation From Commitment See Notice of Deviation, Item C.

b.

Unresolved Items None.

E.

Exit Interview 1.

The inspector met with management representatives denoted in para-graph A. at the conclusion of the inspection on May 9, 1980.

2.

The following subjects were discussed:

a.

Areas inspected.

b.

Deviations identified.

c.

Contractor response to the report.

The contractor was requested to structure his response under headings of corrective action, preventive measures, and dates for each devia-tion.

s.,s 9

Comments by management representatives were generally related to clarification of the findings.

l 1

I l

)

1