ML19326E037

From kanterella
Jump to navigation Jump to search
Submits Supplemental Response to IE Bulletin 80-09, Hydramotor Actuator Deficiencies. Util Review Remains Incomplete Due to Necessity of Consulting Equipment Suppliers.Response Will Be Submitted by 800829
ML19326E037
Person / Time
Site: Byron, Braidwood, LaSalle  Constellation icon.png
Issue date: 07/15/1980
From: Peoples D
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
IEB-80-09, IEB-80-9, NUDOCS 8007250467
Download: ML19326E037 (1)


Text

thb

,[7 Commonwealth Edison e r one First N1tional Plaza. Chicago, lthnois

)

( O M Address Reply to: Post Office Box 767 1

x Chicago, Illinois 60690 July 15, 1980 Mr. James G. Keppler, Director Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatcry Commission 799 Roosevelt Road i

Glen Ellyn, IL 60137

Subject:

Supplemental Response to IE Bulletin 80-09 "Hydramotor Actuator Deficiencies" LaSalle County Station Units 1 and 2; Byron Station Units 1 and 2; Braidwood Station Units 1 and 2; NRC Docket Nos. 50-373/374 and 50-454/455/456/457 Reference (a):

J. G. Keppler letter to C. Reed dated April 17, 1980

,o):

D.

L. Peoples letter to J. G. Keppler dated June 16, 1980

Dear Mr. Keppler:

Your request for information contained in Reference (a) concerning "Hydramotor Actuator Deficiencies", was originally responded to in Reference (b).

For the subject units at LaSalle County, Byron and Braidwood Stations it was indicated that additional time was required to complete the review.

At this time our review remains incomplete due to the necessity to pursue through equipment suppliers the specific information requested in the Bulletin.

It is judged at this time that a complete response will be available no later than August 29, 1980.

In as much as the units in question are not operating. this delay does not present any unreviewed safety concern.

In the event corrective action is required after the review has been completed, our sul equent response will outline the remedial action taken.

If you have any questions in this regard, please direct them to this of fice.

Very truly yours, f

Ibf/

L.

D Peoples Director of Nuclear Licensing dOb Y bN00 cc:

U.S. Nuclear Regulatory Commission Director of Reactor Construction Inspection, 0.I.E.

Washington, DC 20555 8fdE50k/i