ML19326A093

From kanterella
Jump to navigation Jump to search
Insp Rept 50-346/71-01 on 710218-19.No Noncompliance Noted. Major Areas Inspected:Turbine Bldg Concrete Pour,Batch Plant Concrete Ticket Review & Const Status
ML19326A093
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/03/1971
From: Gower G, Oller R, Vetter W
US ATOMIC ENERGY COMMISSION (AEC)
To:
Shared Package
ML19326A084 List:
References
50-346-71-01, 50-346-71-1, NUDOCS 8001310659
Download: ML19326A093 (8)


Text

.. -..

. _ ~

O w

U..S.

ATOMIC ENERGY C0FD11SSION DIVISION OF COMPLIANCE REGION III Report of Construction Inspection CO Report No. 346/71-1 Licensee:

Toledo Edison Company (Davis-Besse)

Construction Permit (CPPR not issued)

Category A Dates of Inspection:

February 18 and 19,1971 Dates of Previous Inspection:

November 5 and 6,1970 t

e. k Inspected By:

G.

. Gower Principal Reactor Inspector 3-3-71

  1. f0L R. E. Oller Metallurgical Engineer 3-3-71 Reviewed By:

W. E. Vetter Senior Reactor Inspector 3-3-71 Proprietary Information:

None SCOPE 4

Type of Facility:

Pressurized Water Reactor Power Level:

872 Mwe Location:

Southwest shore of Lake Erie, Ottawa County, Ohio Type of I.:spection:

Routine - Announced f

8001310

-S

(

).

\\s_/

i

SUMMARY

Safety Items - None.

Noncompliance Items - None.

Unusual Occurrences - None.

Status of Previously Reported Problems grding Toledo Eidson Company's (TECO) implementation of AEC Criterion 1.

Reg / Test Control, since the previous inspection TECO has prepared draf t XI4 implementing procedures to assure proper coordination, testing review mad acceptance of completed systems, etc. on the part of the applicant.

Current construction status does not require utilization of the requir ments of Criterion XI.

TECO plans to have the required procedures completed at the time of the next routine CO inspection and in time for use when required.

This item is to receive follow-up attention.

2.

The applicant has endeavored to establish a tagging procedure to meet

"'s the requirements of Criterion XIV.

During the current inspection, it was learned that the desirability of having a universal tagging system imposed upon all contractors at the site was still under the A-E and construction manager).

Implemainta-discussion with Bechtel (/ is to be worked out 2

in the near future aad in tion of a tagging system advance of any need, according to Jim Lenardson, the Davis-Betse (D-B) QA Engineer. This item will require followup.

3.

TECO's efforts to recruit a Mechanical Engineer as an addition to the TECO.QA. site staff have been unsuccessful.

Discussions with L. E.

Roe,. the TECO Chief Mechanical Engineer and D-B Project Engineer, said that finding a qualified person to fit their requirement has been very difficult.

Efforts will continue in this area, Roe said, until a qualified man is found.

Mr. Roe said that a welding technician from within TECO will be assigned to the site QA staff when Chicago Eridge and Iron (CB&I) starts the containment vessel work. Site QA staffing will continue to receive follow-up attention.

1/ CO Report No. 346/70-3, Section K-2.

/N 2/ CO Report No. 346/70-3, Section N-2.

f

}

G'

-s V

Regarding the lack of specifications, etc. for pumping concreted /

4.

TECO has now learned that concrete is to be pumped for certain portions of the plant and has taken action to have the concrete specifications include the appropriate ACI-301 references to pumped concrete.

Other Significant Items - The previous inspection report stated that the applicant's report to DRL on the plant bedrock " Verification and Remedial Treatment Program" would be submitted in January 1971. Contrary to this statement, TECO informed the inspector that this report is now being finalized and should be sent to DRL by April 15, 1971.

Management Interview Personnel in Attendance E. F. Doerr - Acting General Superintendent, TEC0 G. W. Eichenauer - QA Representative (Civil), TECO M. R. Stephens - Project Construction Manager, Bechtel A. S. Martin - QA Engineer, Bechtel D. P. Eisenhardt - QA Engineer, Bechtel D. L. Reddick - Project Field Engineer, Bechtel The following items were discussed at the conclusion of the inspection and later (by phone) with Mr. L. E. Roe, TECO Chief Mechanical Engineer and D-B Project Engineer, who was unable to attend the management interview.

1.

The TECO and Bechtel representctives were informed that,,during the concrete pour of the turbine building slab, the inspectors observed concrete handling practices which appeared to be questionable.

Specifically, the flexible drop chute (located at the end of the belt conveyor) was, at times, observed to be 000 high and concrete was allowed to pile up excessively beneath the chute. Leveling of the resulting piles may have led to horizontal flow of the concrete and other conditions not conducive to proper consolidation of concrete.

Both Bechtel and TECO acknowledged the above criticism... admitting that there was room for improvement in this area and said that action would be taken as required. Bechtel pointed out that the turbine building slab was not a Q-list item but that they were treating the

_ pour as a Q-list item so that A. Bentley & Sons (AB&S) would gain additional experience with respect to concrete placement practices.

(II-A-3) l l

3/ C0 Report No. 346/70-4,Section II.B.5.c.

O t

i v

l

= _ _ _

. _. ~.

f I

(*

  • m

,r-' >

.s

~

l 4

2..

Regarding the inspector's.2 view of Fegles-Power Service, Inc. (Fegles)

Quality Assurance and Construccion Procedures for the reactor shield j

building, it was observai that the appropriate aspects of the AEC QA' Criteria appeared aave been included. However, the specific I

' duties of Fegles QC inspectors did not appear to be sufficiently identified. Moreover, it was not apparent that the inspectors were separated from the construction work supervision function.

l Bechtel and TECO stated that they had previously recognized the t

possibility that the Fegles QA Manual may be criticized in the above

' (

described areas.. Consequently, the applicant and Bechtel plan to meet with Fegles to discuss an appropriate supplement to the manual which would clarify the above points. According to M. R. Stephens,

l Bechtel Construction Manager, corrective action is to be completed

[

prior to resumption of concrete work on the shield building.

(II-C)

I 3.

TECO and Bechtel personnel were informed that the inspectors had reviewed a total of 52 batch plant concrete tickets, for a recent l

concrete pour, and had noted the omission of a dumping time on one ticket and the countersign signature by Pittsburgh Testing Laboratory (PTL) on another.

It was explained that the undocumented dumping time had been resolved by reference to other data. The inspectors pointed out that the omissions noted represented approximately 4% of the total' ticket sample and, consequently, could be significant if the omissions were of a more serious nature. In conjunction with this observation, it_ was pointed out that an earlier and more thorough QC review of the concrete batch plant tickets appeared to be in order.

Both TECO and Bechtel agreed that a more timely and thorough QC review should be made of the batch plant tickets and stated that r

improvements are to be made in this respect.

(II-B) 4.

It was brought to the attention of those present during the management interview and to the attention of L. E. Roe, later by telephone, that TECO had not met a commitment made during the previous inspection to j.

augment the site QA ctaff by January 1971 with the addition of a i

Mechanical Engineer. A further comment was that Compliance had, from i

the beginning, considered TECO's site staffing to be marginally i

. acceptable with ' respect to total numbers and disciplines. This l

concern has, in the past, been tempered by consideration of the status of the project and lack of an apparent need.

[

' TECO representatives and, in particular, Mr. L. E. Roe, were urged I

to consider the need for augmenting their site QA staff in the very near: future in view of the impending start of an extensive construction f

' effort.

Mr. Roe stated that TECO is and has been recruiting for a t

s i

+,

..,_.m~

-,,,r_..,_..

-, _,.,_. ~.,_,...

..,, -...~._,.

  • ~

m

[sT i

5-i

\\,_,]

Mechanical Engineer but has not been successful in finding the right man for the job. He added that additional steps will be taken to expedite the hiring of a Mechanical Engineer.

5.

Regarding the development and implementation of a suitable tagging procedure to meet the requirement of the AEC Criterion XIV, the applicant said that work will coo *inue on this item and a workable system will be implemented by the

-.e it is needed.

I.

Persons Contacted In addition to those listed above, the following persons were contacted:

T. (NMI) Lysons - Civil Superintendent, Bechtel G. N. Blackham - Field Engineer, Bechtel R. J. Segar - Construction Supervisor, AB&S E. J. Subleski - QC Engineer, AB&S G. R. Barnes - Senior Technician, PTL V. L. Smith - Supervisor, Nicholson Concrete & Supply Company D. (NMI) Ponke - Technician, Michigan Testing

[V}

II.

Results of Inspection A.

Attachment C - Followup Observation of Work (4605.06)

Compliance requested, during a previous inspection, to be notified when a significant concrete pour was to be made at the D-B plant.

Such a pour was made on February 18 and 19,1971, and Compliance inspectors were at the site to observe.

The pour under observation was the turbine building base slab, consisting of a single nine foot thick pour requiring about 2650 cubic yards of concrete. The turbine base slab is not a Q-list item.

However, TECO had previously informed C0 that the base slab would be treated as if it were a Q-list item for training purposes.

1.

Preplacement QC Inspection, a.3.

An AB&S field inspection report (Form 10) had been prepared l

and signed off.

This aspect of the pour appeared satisfactory.

l l

2.

Slump, Strength Entrainment and Tests, a.5.

l Slump and entrainment tests were observed being made at the pour site.

Records of the same type of tests made at the batch l

plant were reviewed and found to be within the specifications.

l Strength cylinders were also taken at the pour site and at l

fs the batch plant.

e s

t 4

3

~g'.

Results of Inspection (continued) i 1*

3.

Placement Made Properiv, a.6.

Observations of concrete placement indicated acceptable practices with the following exception:

The flexible drop chute (through which the concrete was dropped to the placement location) was observed to have been lif ted too high charing periods of adjustment.. Also, on occasion, the concrete was permitted to pile up beneath the drop chute which required subsequent leveling.

Both of the above practices, it was 4

pointed out to the applicant, would produce aggregate segregations.

l i

Bechtel acknowledged the criticisms and stated that with i

l respect to the occasional excessive drop chute height, concern should be resolved af ter more experience has been gained through operation of the new conveyor equipment. Regarding i

the excessive pileup of concrete, the applicant indicated

]

that steps will be taken to watch for, and correct, any deficiencies noted.

)

4.

Rebar Splices Made Properly, a.8.

g I

Rabar splices were not being made during this inspection.

i Followup is required on this item.

4 5.

Proper Delivery of Concrete, b.5.

i

[

QC activities associated with the delivery of concrete were reviewed and found to be acceptable.

j 6.

Proper QC Inspections, b.8.

l.

Quality control inspection of the concrete pour observed sppeared to be adequate.

B.

Attachment C - Followup Record Review, b.2.

During the review of 52 batch plant concrete tickets for a previous Q-list pour, the inspectors noted the omission of a PTL counter-1' '

sign signature on one ticket and the omission of a dump time on another.

These discrepancies were brought to TECO and Bechtel's attention... not so u much because the omissions were of a serious nature but because the omissions represented about 4% of the audit sample and, as such, it appeared appro-priate for those responsible for the QC review of the tickets to make a more timely review and to be more thorough.

l.

I f-i r

,-n,.

,-e,n

.---+-n--..rn<vn.,.,----n----,r---,---,,~--w-.

- ~, - -v

--r-

-r--

.m e

~ C_s L :

/

s Results of Inspection (continued)

The omitted dump time was obtained later and found to be within the time limits by reference to other records. No discrepancies were noted during the ticket review other than those noted above.

C.

Review of QA Manual for Fegles-Power Service, Inc. (Fegles)

The inspectors reviewed the QA Manual and work performance pro-cedures for Feglas, the contractor responsible for slip forming the D-B shield' building.

The manual appeared to contain the appropriate requirements for a workable QC system with the following exception. Although it appeared that Fagles had provided for adequate QC inspection and documentation, the manual did not appear to sufficiently identify personnel responsible for the inspection effort. Moreover, it was not apparent that those assigned to do the QC work were separated from the supervision of the construction effort. TECO and Bechtel were informed of the above apparent shortcoming. They acknowledged the problem and said that Fegles will be requrested to clarify the manual in the above mentioned area by way of a supplement. This supplement is to be completed and approved, according to TECO, before work resumes on the shield building.

D.

Review of QA Audit Programs Discussions were held with Bechtel and TECO regarding their plans and procedures for auditing the contractor's QC activities at the site.

Both TECO and Bechtel provided the inspectors with audit schedules,

documentation of audits performed and the procedures and check sheets utilized in the performance of tha audits. No discrepancies were noted during this review.

E.

Results of Inquiry Into Aircraf t Overflights Mr. Lenardson and other D-B site personnel were questioned regarding the possibility of frequent or periodic aircraf t flights over, or near, l

the D-B site.

Mr. Lenardson was acquainted with the overflights at Big Rock Point and stated with confidence that a similar problem did not exist at - the D-B site.

III. Construction Status The turbine building. foundation slab was poured during the inspection.

A section.of the auxiliary building foundation has been poured.

Reinforcing steel for one of the auxiliary building support structures has been placed, Fegles has set up a slip forming rig for the shield wall and made concrete i

l placements of the wall up to-grade level (583'-6").

Overall construction l

'y is estimated to be less than 5%.

l

m 8.

Pumped Concrete Mr. Lenardson informed the inspectors that the pumping of concrete j

would be employed at the Davis-Besse site in the near future and that Bechtel had initiated the preparation of the specification and 4

placement procedures. This item will continue to be followed.

9.

Shield Building Tolerances Bechtel Specification No. 7749-C-38, Revision 1, listed, among other requirements, various construction tolerances.

Section 10.3.2, Plumbness, states that "the cylindrical wall of the completed Shield Building shall be plumb within 4 inches (four inches) from top to bottom and shall be not more than 1 inch (one inch) out of plumb in any 25 feet (twenty-five feet)".

Bechtel and Fegeles Construction Company are in the process of settling a dispute regarding the later specification on plumbneFs.

Bechtel has stated their belief that the out-of-plumbness specification has been exceeded by 1/8 inch between elevations 109'-0" and 129'-6".

Fegeles Construction Company does not agree with this interpretation of the i

specification.

The dimensions of the shield building have been transmitted to i

Bechtel's Gaithersburg, Maryland office for an engineering evaluation.

The inspector asked that the engineering evaluation.be made available for review during his next routine visit. No other deficiencias were noted.

l

(

l.

l p V