Attachment 1 to ULNRC-0655 1 Page 1 off REGULATORY COMMITMENT UPDATE The following table identifies those actions previously identified as regulatory commitments by Arneren Missouri in Reference 1. Please direct questions regarding these commitments to Bruce Huhmann at (573) 694-6741.
Regulatory Commitments and Completion Schedule Modification Committed Commitment Status Completion Date Tracking Number Install Anchorage to the Alternate December 3 1, 2020 5043 1 Complete Emergency Power Supply transformer (XPBO5).
Provide a minimum of 1 -inch December 3 1, 2020 50432 Complete clearance around two fire sprinkler heads located on the 1 974 elevation of the control building at grid C4 & CC, and gridC2&CB.