ML19325C662

From kanterella
Jump to navigation Jump to search
Submits Review of Each NRC Position Taken Re NRC Bulletin 88-010,Suppl 1.Installed Breakers Purchased Since 830801 Const Not Reviewed Per Action 4.a Since Not Installed as Replacements or Mods
ML19325C662
Person / Time
Site: Beaver Valley
Issue date: 10/09/1989
From: Sieber J
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IEB-88-010, IEB-88-10, NUDOCS 8910170153
Download: ML19325C662 (5)


Text

"]9{T [

g' g ~ _

n

'I '.., [g fl '

Stuppingprt, PA 150774004

  • > f.

f

,s 49 1

1 i

ggg I4 2 643535 e'

October 9, 1989 i

Ui1S. Nuclear' Regulatory Commission e

Attn:

Document Control-Desk '

if Washington, DC' 20555 h

t'

Reference:

Beaver Valley Power Station, Unit No. 1 and No. 2 BV-l' Docket No. 50-334~, L! cense No. DPR-66 BV-2 Docket No.-50-412, License No. i>'F-73 NRC Bulletin 88-10, Supplemer.t 1 Gentlemen:

g Previous. actions to resolve Bulletin 88-10 have-been reviewed

as.requestedDin Supplement 1.

.The,;following: review of each NRC position is intended to documentTour; understanding of Supplement 1 to IE Bulletin 88-30.

NRC Position 1

-If" - Circuit' Breakers (CBs) are traceable to an original plant 3

construction-order and the CBs were received prior to August 1983, there is reasonable assurance that the CBs are. acceptable and no

' additional traceability is required.

J Bapponse j

It-is our understanding that this position is not intended to imply that _the converse is also true.

That is, if a CB is D21

traceable to an original plant construction order then there is D21

reasonable

' assurance...

Duquesne Light Company has accomplished action' 4.a of the original'bul3etin which states,

" Identify 3 all-molded-case CBs that have been purchased between D

~ August E1,:1983-and August 1, 1988, and installed in safety-related j

applications as. replacements or installed during modifications."

Duq0esne. Light ' Company _has not verified that all other it. stalled 1 breakers are
traceable to the original plant construction order.

. Installed-breakers : purchased since August 1, 1983 for construction

=

- o f -- BVPS-2 (Licensed 1987) were not reviewed par action 4.a since they were' not installed as replacements or modifications.

These particular breakers.were subjected to a formal testing program s

based Lon-NEMA AB1 during construction.

Examination of test

procedures.used at that-time shows only minor differences from the test criteria presented in the Bulletin.

pl 9910170153 891009 3

r PDR ADOCK 05000334 S

I o

PDC i

n L t-.

a. ' --

p 7

g-Bs4hcr'VallOy Pow 0r StttiCn, UnitLNo3. 1-&'2

'i

  • Docket No. 50-334, License No. DPR-66 LDocket1No. 50-412, License No.-NPF-73 L.

' NRC. Bulletin.88-10, Supplement 1~

Page 2-l NRC Pos#. tion 2 Visual inspection and physical examination of the CBs by the E

circuit breaker manufacturer (CBM) is not considered adequate to

. meet 'the requested traceability provisions of Bulletin No. 88-10.

Although-visual-inspection and physical examination by the CBM may

. provide a

reasonable basis that the CBs have not been opened or altered in a

substantial

way, there-is no reasonable assurance that 'the CBs have not been previously used or subjected to' service conditions that mdy have adversely affected the performance capabilities.of the CBs..

l Response-Duquesne. Light Company did not rely on visual examinations as c

. basis.for-accepting any circuit' breaker under Bulletin 88-10.

i

NRC Position 3 h

Item 4 of the actions requested in Bulletin No. 88-10 applies only to CBs that were purchased and installed after' August 1, 1983.

l L

Engponse 1

This position ' appears to be a restatement of action 4.a of the original bulletin.- Duquesne Light Company has accomplished action l

4.a ef1the original Bulletin.

l NRC Position 4 If~ an addressee identities any CBs as nontraceable during tne

- review. requested by Bulletin No. 88-10, it should take appropriate i

corrective actions as required by Criterion XVI of 10 CFR Part 50,

{

' Appendix B.

As part of these corrective actions, the NRC expects addressees-to assess the acceptability of all installed safety-1 related CBs that were procured-under the same purchase orders as the nontraceable CBs.

Egesonse l

This position appears to address situations where the entire i

purchased quantity of a

particular non-traceable breaker is no longer on-hand in the storeroom and action 4.a of the Bulletin

-(identification of installed breakers) was not required.

As previously

stated, BVPS has accomplished action 4.a of the original Bulletin.

l s-s e-

. _.. - - ~ -., - -,_

p i

Be 90r Villcy Pawcr Station, Unit No3. 1&2 e' Docket No-50-334,1 License No. DPR-66

' Docket No. 50-412,' License No. NPF-73

NRC Bulletin 88-10, Supplement 1 Page 3 j

-1 NRC Position 5

]

lIn an effort to limit the number of nonconforniiLg CBs in 1

safety-related

systems, nontraceable CBs that were installed or j

are being maintained as stored spares as of August 1, 1988, and i

that successfully pass all tests specified~ in Attachment 1 of Bulletin' No.

88-10 are considered acceptable for use only as replacements for safety-related-CBs that are found to be nontraceable during the review requested by-Bulletin Ho. 88-10.

These breakers may not be used as safety-related replacements during other activities such as planned plant modifications or routine maintenance.

i ResDonse Although the original bulletin placed no restrictions on the use

of stored brehkers which passed the Attachment 1 test, Duquesne Light Company reserved the use of such breakers only as a last

. resort (replacement of obsolete breaker styles for example).

Since our actions under Bulletin 88-10 are complete and did not require the use of tested spares to replace. installed 1

non-traceable

breakers, Duquesne Light Company no longer requires this option to be available.

NRC Position 5 For CBs etored as spares that were not procured directly from the

CBM, each individual CB should be reviewed in order to establish i

-proper. traceability, regardless of the number of CBs.

l -

Resnonsa L

l Since previous conversations with NRC staff indicated their awareness -that these breakers are not uniquely identified and that documentation is not uniquely tied to individual breakers, it H

appears : that this position was intended to prohibit " sampling" of j

l stored spares.

Duquesne Light Company has not used sampling as the oasis for acceptance of breakers under Bulletin 88-10.

NRC Position _2 s

l' All safety-related CDs from the same procurement order are L

considered traceable provided that 1) the order was procured

.directly from a

CBM having a

quality assurance program in L

,accordance with 10 CFR Part 50, Appendix B, 2) the CBM has been audited. by the addressee in accordance with Appendix B, 3) the CBs were ordered as safety-related, and

4) documented evidence has E

-been furnished to the addressee, such as a

certificate of

compliance.
However, if safety-related CBs were procured from a 1

l

BethOr?Vallcy Powbr Station, Unit Nos.~1 & 2

,J Dooket No. 50-334, License No. DPR-66 Docket No. 50-412, License No. NPF-73 NRC Bulletin'88-10,-Supplement 1 o

Psge 4 L

' vendor aether than the CBM,_a certificate of compliance by-itself

-)

l~

J~

is not considered an adequate basis for establishing

. traceability.

In such

cases, traceability of individual O

procurement orders, should be established through the roview of

~

0 procurement or shipping records back to the' CBM.

Telephone H

discussions with the CBM or vendor are not acceptcble for L

establishing-a basis for traceability.

Traceability to a

warehouse ~ -facility controlled by the CBM is considered equivalent to traceabilit ?r.to the CEM.

i li Resoonsg The overall intent of this position is unclear because it appears to-require an Appendix B CA program controls in order to conclude j

traceability to the CBM.

The original bulletin recognized the 1

fact that molded-case circuit breakers are likely to be commercial 1

grade items which are used in safety related applications.

In such

cases,

_the manufacturer may not have 1an Appendix B QA L

Program, i

l l

Since we ; suspect that this posit' ion was not intended

  • o be L

inconsistentf with the traceability definition presented in the original

bulletin, we have concluded that this position was o

-intended to, limit the.use of certificates of compliance (COC) by q

themselves-to purchases where Appendix B was rigorously applied.

Since COCs do not 'normally certify the' origin of purchased

~

l

material, Duquesne Light Company has not relied on COCs as a basis-

.for establishing traceability to the CBM regardless of the p

application of Appendix B to the purchase.-

No reliance was-placed l

on verbal communicationa with the vendor as the sole basis.for establishing traceability.

We believe that our understanding of thc supplement is

' consistent with your intent.

Plertse contact my' of fico if there are-further. questions on this matter.

Very truly yours, 4

J.

D. Sieber

)

l Vice President Nuclear Group 1

cc:

Mr. J.

Baall, Sr. Resident Inspector Mr. W. T. Russell, NRC Region I Administrator

)

l Mr.

P.

Tam, Sr. Project Manage.

1

m.

.a p 3

_6

,hA,bf.-

,4, w

.;- COMMONWEALTH OF: PENNSYLVANIA) e

)~

SS:

L.4

^ COUNTY OF BEAVER

)

7 on this i

day of d

2 J//

, 1989, before:me,(

/ /,1> b bkV/,

a Notary Public in and for.sairi

./

f.'

_ Commonwealthand-County, persor. ally appeared J.

D. Sieb'er, who being'

i dhly; sworn,

' deposed,- and said-that (1) he ' is Vice-President of=

Duquesne-Light,

.(2) -he is. duly authorized to! execute and file the foregoing Submittal on-behalf of said Company, and (3) the statements-set.forth; 'in the SuF.nittal arce true and correct to the best of hisi knowledge, information and belief.

v a

't

.1,

?

! ' Y-l

-i.

L'

,h\\

C i'

))/b h) "lW&ff Netana! Seal

. i

$ hela M. Fat l ore, tatary Putic

$9;ptgert Boro, Deaver County My Comucen Enwee Oct.23,1939 r

. Member Pennsylvane Assocateof PAmnes 5

l.'. c:.

m

&!!-N

~ - - - - -