ML19323G845

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-382/80-08 on 800407-10.No Noncompliance Noted.Major Areas Inspected:Const Activities Re safety-related Cable Pulling & Terminations
ML19323G845
Person / Time
Site: Waterford 
Issue date: 04/22/1980
From: Crossman W, Kelley D, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19323G840 List:
References
50-382-80-08, 50-382-80-8, NUDOCS 8006090097
Download: ML19323G845 (4)


See also: IR 05000382/1980008

Text

.

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Report No. 50-382/80-08

Docket No. 50-382

Category A2

Licensee:

Louisiana Power and Light Company

142 Delaronde Street

New Orleans, Louisiana 70174

Facility Name: Waterford Steam Electric Station, Unit No. 3

Inspection at: Waterford Site, Taft, Louisiana

Inspection Conducted: April 7-10, 1980

Inspector:

/hw

th!'p

.

D. L. Kelley, Reactor Insfecto[, Projects Section

Dale

'

Reactor Operations and Nuclea# Support Branch

Reviewed:

e

__m>

R."C. Stewar't, neacto'r Inspector, Projects Section

Date

'

Reactor Construction and Engineering Support Branch

9-7. bliak

+h +/O

T. F. Westerman, Chief, Projects Section

Date

Reactor Operations and Nuclear Support Branch

2.

8g

Approved:

W. A. Crossman, Chief, Projects Section

Date

Reactor Operations and Nuclear Support Branch

Inspection Summarv:

Inspection on April 7-10, 1980 (Report No. 50-382/80-08)

Areas Inspected:

Routine, unannounced inspection of construction activities

related to safety-related cable pulling and terminations. The inspection

involved twenty-seven inspector-hours on site by one NRC inspector.

Results:

No items of noncompliance or deviations were identified.

WO6090

.y y

_ _ _

.

.

.

DETAILS

1.

Persons Contacted

Louisiana Power and Light Company

  • L. L. Bass, Project QA Engineer
  • T. F. Gerrets, QA Manager
  • C. Chatelain, QA Engineer
  • J. Woods, QC Engineer
  • B. Toups, QA Engineering Technician
  • B. Brown, QA Engineer

Others

  • E. J. Ritzman, Project QC Manager, Fischback and Moore
  • L. A. Stinson, Manager, Site Quality Program, ESI
  • B. L. Collin, QC Engineer, Fischback and Moore

J. Debruin, Project Engineer, ESI

  • Denotes those attending the exit interview.

The IE inspector also interviewed other licensee and contractor personnel

including members of the engineering and QA/QC staffs.

2.

Safety-Related Cable Pulling Activities

The IE inspector reviewed the following procedures relating to the inst 311ation

and tasting of safety-related cables:

>

CP-306, R3, 3/27/79, "CP for Cable Pulling"

CP-405, R3, 1/26/79, " Insulation Testing of Cables and Equipment"

The review was conducted to verify that the procedures had the required

reviews and approvals, and that the procedures were in accordance with the

licensee's commitment and NRC requirements.

In addition to the above review, the IE inspector randomly selected the

record of installed cables to verify that:

The cables had been irstalled in accordance with procedures.

The installed cables had been tested in accordance with approved

procedures as required.

The cables were properly identified as required.

Any rework was accomplished in accordance with approved procedures.

,

-2-

. _ _ _ _ _ _

.

.

The following cables were randomly selected for records review:

30734A-SA - From MCC 3A315S(2) to Cooling Tower / Dry Fan 4-3A

30862K-SA - From Aux. Panel 1A to CP-8

30191J-SMA - From CP-22 to CP-7

31080D-SB - From Aux. Panel 2D to CP-44

Rework documents for cable 30191J-SMA; FCRE-1064

Testing records for the above cables

The review also consisted of verifying that the cable testing equipment

was in compliance with required calibration requirements.

No items of noncompliance or deviations were identified.

3.

Safetv-Related Cable Termination Activities

The IE inspector reviewed procedure CP-307, R3, 12/28/79, " Cable Terminations

and Splices," to verify that the ; ocedure had the required approvals and

were in accordance with the licensee's commitments and NRC requirements.

Three of the cables selected for review in paragraph 2 were selected for

review.

The review consisted of verifying that the required procedures

had been used and that the termination tools used had been calibrated as

required.

In addition, the IE inspector reviewed the training records of the individuals

performing the' termination activities to verify they had been instrucced in

the correct method of terminating safety-related cables.

No items of noncompliance or deviations were identified.

4.

Plant Tour

The IE inspector toured the plant, examining electrical equipment, cable

trays and cables and cable terminations.

Particular attention was made of the routing paths inside safety-related

cabinets and paneis in relation to separation of redundant safety channels.

The IE inspector noted that in panel CP-7 in the Control Room, the length

of the channel separators from the front to the back of the panel and the

match up of the conduit block out separators may or may not adequately

satisfy General Design Criteria No. 3 and No. 22 of Appendix A to 10 CFR 50.

-3-

.

.-

,

This possible problem area was pointed out to_the licensee. This item

will remain unresolved pending a review of the licensee's evaluation.

No items of noncompliance or deviations were identified.

5.

Unresolved Items

Unresolved items are those items for which further information is required

to determine whether the items are acceptable items, items of noncompliance,

or deviations. An unresolved item is discussed in paragraph 4.

6.

Exit Interview

The IE inspector met with licensee representatives (denoted in paragraph

1) on April 10, 1980, to summarize the scope and results of the inspection.

!

f

4

-4-

,

_

_

___

...