Advises That Planned 800418 Submittal of Final Rept Re Weld Discrepancies in Reactor Vessel Structural Support Will Be Delayed Until 800618,due to Amount of Time Required to Take Boat Samples
ML19323D568
Person / Time
Site: Beaver Valley
Issue date: 04/17/1980
From: Woolever E
DUQUESNE LIGHT CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML19323D563 List:
References
NUDOCS 8005210689
Download: ML19323D568 (1)


Text

_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

'AP (412) 456-6000 433 Sisin AverNo

$7'"^

April 17, 1980 United States Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 ATTENTION:

MR. BOYCE H. GRIER, DIRECTOR

SUBJECT:

Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 Weld Discrepancies in Reactor Vessel Support Structure Significant Deficiency 79-05 Gentlemen:

Our letter dated, January 4, 1980, stated that we planned to issue the final report on the Weld Discrepancies in Reactor Vessel Structural Support (Neutron Shield Tank) by April 18, 1980. Due to the amount of time required to develop the jig for taking boat samples in the area under question, we would like to extend the planned date for the issue of the final report to June 16, 1980. We feel this will allow sufficient time to take more samples, have them analyzed and resolve the reported def-ici scy.

DUQUESNE LIGHT COMPANY By 14 J. Woolever Vice President cc:

Dr. V. Stello (15)