Informs That Util Was Unable to Meet 800428 Deadline Re Calculations That Provide Backup Support for Ter.Current Target Date for Submittal Is 800523
ML19323A940
Person / Time
Site: Crane Constellation icon.png
Issue date: 05/02/1980
From: Hovey G
METROPOLITAN EDISON CO.
To: Jay Collins
Office of Nuclear Reactor Regulation
References
TLL-201, NUDOCS 8005070478
Download: ML19323A940 (1)


Text

. _ _ _ _ _ _ - - _ _ _ _ _ _ - _ _ -

8006070478 Metropolitan Edison Company

[j h

f4" y-)

y Post Office Box 480 Middletown, Pennsylvama 17057 717 944 4041 Writer's Direct D;al Narroer May 2, 1980

'"LL 201 TMI Program Office Attn:

J. T. Collins, Deputy Program Manager U. S. Nuclear Regulatory Commission c/o Three Mile Island Nuclear Station Middletown, Pa.

17057

Dear Sir:

Three Mile Island Nuclear Station, Unit II (TMI-2)

Operating License No. DPR-73 Docket No. 50-320 Submerged Demineralizer System Our letter, TLL-160, dated April 10, 1980, transmitted the Submerged Demineralica:

System Technical Evaluation Report. In this letter we stated that the calculations that provide backup support for the TER would be submitted by April 28, 1980.

We were unable to meet this schedule. We are currently targeting May 23, 1980 for submittal of the calculations.

Sincerely,

/s/ G. K. Hovey G. K. Hovey Director-TMI-II GKH:LJL: hah cc: