Forwards IE Insp Rept 50-327/80-09 on 800224-25.No Noncompliance Noted
ML19323A774
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 03/14/1980
From: Bryant J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML19323A775 List:
References
NUDOCS 8005060003
Download: ML19323A774 (2)


Text

U i

UNITED STATES NF D

8

(

t, NUCLEAR REGULATORY COMMISSION

' aE REGION 11 1

o, 101 MARIETTA ST N.W., SUITE 3100 l

8 800$

g*#.

,o MAR 141980 Q

ATLANTA. GEORGIA 30303 In Reply Refer To:

RII:PKV 50-327/80-09 Tennessee Valley Authority ATTN:

H. G. Parris Manager of Power 500A Chestnut Street Tower II Chattanooga, TN 37401 Gentlemen:

This refers to the inspection conducted by P. K. VanDoorn of this office on February 24-25, 1980 of activities authorized by NRC Construction Permit No.

CPPR-72 for the Sequoyah Nuclear Plant facility, and to the discussion of our findings held with J. M. Ballentine at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the enclosed inspection report. Within these areas, the inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.

If this report contains any information "that you (or your contractor) believe to be proprietary, it is necessary that you make a written application within 20 days to this office to withhold such information from public disclosure. Any such application must include a full statement of the reasons on the basis of which it is claimed that the information is proprietary, and should be prepared so that proprietary information identified in the application is contained in a separate part of the document.

If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to discuss them with you.

Sincerely,

. C. B eting Chie Reactor Construction and Engineering Support Branch

Enclosure:

(See Page 2)

Tennessee Valley Authority h0%R 141980 4

Enclosure:

Inspection h0 port No. 50-327/80-09 cc w/ encl:

G. G. Stack, Project Manager P. O. Box 2000 Daisy, TN 37319 J. M. Ballentine Plant Superintendent P. O. Box 2000 Daisy, TN 37319 J. F. Cox 400 Commerce Street W10C131 C-K Knoxville, TN 37902 D. L. Lambert, Project Engineer 400 Chestnut Street Tower II Chattanooga, TN 37401 T. B. Northern Construction Engineer Post Office Box 2000 Spring City, TN 37381 E. G. Beasley Tennessee Valley Authority 309 Grant's Building Knoxville, TN 37902