Submits Application to Amend Export License,Changing Contractual & Delivery Dates,Increasing Reactor Power Level & Increasing Reactor Costs.Also Applies for SNM License
ML19323A178
Person / Time
Site: 05000585
Issue date: 03/20/1980
From: Mowry W
GENERAL ATOMICS (FORMERLY GA TECHNOLOGIES, INC./GENER
To: Peterson M
NRC OFFICE OF INTERNATIONAL PROGRAMS (OIP)
References
IEL-1162, NUDOCS 8004170360
Download: ML19323A178 (2)


Text

.

s

?&

ENERAL ATOM *=

  • ~

GENERAL ATOMIC COMPANY g y 2_$,.

L - 7.~In Reply Po. Box 81608 cM35 March 20,'1980 Refer To:

IEL-1162 8

E

"'^

,'.7/I:f'i?

' :.D g(

Ml*L SFC'iD3 Dr. Marvin Peterson, Acting Director 3

Export / Import & International Safeguards Office of International Programs U.S. Nuclear Regulatory Commission Washington, D.C. 20555 I

Subject:

Amendment to Application for Utilization Facility Export License; Bangladesh.

~

Ref:

(a) General Atomic Co. letter IEL-821, dated 5/24/77.

Dear Mr. Peterson:

General Atomic Company made application for a utilization facility export license in its May 24, 1977, application, Ref. (a).

In the intervening months since May 1977, certain changes have occurred which require an amend-ment to our application. Among them are revised contractual and delivery dates, an increase in reactor's power level from 1 Mw thermal to 3 Mw ther-mal and an increase in reactor costs and certain other changes in nuclear parameters resulting from fuels being currently supplied to overseas reac-tors.

In addition, it is our understanding that Bangladesh has now become a member of the IAEA and we understand they have agreed to apply IAEA safe-guards to the reactor facility and its fuels.

General Atomic's previous application, made pursuant to 10 CFR 50, in our view, is still valid. Correspondingly we amend information in that appli-cation so that the new export license, anticipated to be issued pursuant to 10 CFR 110, will contain the desired. authority for exporting the cur-rently planned reactor facility. The necessary changes will be treated in the paragraphs below.

In our 1977 application reference was made that the fuels would be subject of an export license pursuant to 10 CFR 70 and that the export of americium-beryllium sources would be made under 10 CFR 36.

The fuels' application con-tinues to be the subject of a separate application but will now be made pur-suant to 10 CFR 110. Under separate cover but essentially coincident with this letter is another letter requesting the XSNM license for the reactor fuels and fission chambers.

We understand tht '- the agreements for cooperation are moving ahead and the export license may be issued in the near future. Accordingly we are amend-ing the utilization facility license application and making application for the SNM at this time.

5004170 @

4 Marvin Peterson IEL-1162 The original application indicated the first shipment of reactor components was scheduled on or about July 1, 1978. This date has now changed to May 1981. The final shipment of fuels and components is scheduled for July 1982. The fuel loading and checkout are now scheduled for completion in November 1982. Correspondingly we request that the license be valid through

~

at least June 1983 to accommodate any unforseen delays in startup or the supply of faulty components under warranty repair.

Paragraph 3, page 2, of the referenced application indicated that the cost of the items being exported would be approximately $1.7 million.

Increased costs of components and fuels now requires that a value of $3.5 million be substituted for the value of the materials exported.

t Paragraph 4, page 2, indicated a steady state power of the reactor would be approximately 1,000 kw thermal. The purchaser has exercised certain contract l

options and the reactor has now been designed to accommodate a steady state power of 3000 kw thermal.

1 Attached to the original application was a general specification sheet for the reactor. While the information in that attachment remains essentially valid, increasing the power level of the reactor with fuels currently desig-l ned for export with TRIGA requires an additional number of fuel elements and an increased loading of uranium per element. Accordingly, under the nuclear parameters sub-heading Fuels, General Atomic will be exporting to the facility approximately 110 fuel elements, each containing approximately 100 gms U-235 for a total loading of 11 kg U-235.

r Other information in the application remains the same.

We, therefore, request that the license be issued to authorize the export of a TRIGA Mark II Reactor to Bangladesh with power levels up to 3,000 kw thermal and having a value of

~$3.5 million.

Very truly yours, I

William R. Howry Licensing Administrator Nuclear Materials Control Division WRM:hes i