Advises That Engineered Safety Feature Info Required by NRC Will Be Delayed Due to Conflict W/Schedule for Response to IE Bulletin 80-06.Response Will Be Submitted by 800531
ML19322E587
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 03/24/1980
From: Rich Smith
VERMONT YANKEE NUCLEAR POWER CORP.
To: Ippolito T
Office of Nuclear Reactor Regulation
References
IEB-80-06, IEB-80-6, NUDOCS 8003280466
Download: ML19322E587 (1)


Text

'

VERMONT Y ANIGE N UCLEAR power CORPOR ATIox SEVENTY SEVEN GROVE STREET B.3.2.1 WVY 80-47 RUTI.AND, VERMONT 05701 REPLY TO:

ENGINEERING OFFICE TURNPIKE RO AD WESTDORO. M ASS ACHUSETTS 01581 TELEPHONE 6 3 7-3 6 6-9 01 g March 24, 1980 United States Nuclear Regulatory Commission Washington, D. C.

20555 Attention: Office of Nuclear Reactor Regulation Mr. T. A. Ippolito, Chief Operating Reactors Branch #3

References:

1) License No. DPR-28 (Docket No. 50-271)
2) Letter, T. A. Ippolito (URC) to R. L. Smith (VYNPC) l dated March 12, 1980
3) IE Bulletin No. 80-06, " Engineered Safety Feature (ESF) Reset Controls" dated March 13, 1980

Subject:

Request for additional Information for Bypass and Reset of ESF For Vermont Yankee

Dear Sir:

Reference (2) requested that we review all the Engineered Safety Features (ESF) at Vermont Yankee to determine whether or not we met the criteria given in that Reference. In addition, we were required to submit a large amount of descriptive information regarding the ESF. All this was requested within thirty days of our receipt of Reference (2).

Reference (3) requested a review of all ESF at Vermont regarding reset controls; this is also a portion of the review required by Reference (2).

Reference (3) required a response within ninety days.

In view of the large amount of information requested in Reference (2),

the duplication of requirements between References (2) and (3), and the conflict of schedules (thirty vs. ninety days) we are unable to provide the information requested in Reference (2) in the time allowed. However, we will submit the information requested by May 13, 1980.

We trust the information provided above is acceptable, however, should you have any questions, please contact us.

l Very truly yours, i

VERMONT YANKEE NUCLEAR POWER CORPORATICN Y

l R. L. Smith Licensing Engineer RLS/smw 80032 Pr 966