ML19322E366

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-382/79-02 on 800129-31 & 0201.No Noncompliance Noted.Major Areas Inspected:Followup of in-process Welding Activities on RCP Boundary Piping & Followup on Response to IE Bulletin 79-02
ML19322E366
Person / Time
Site: Waterford Entergy icon.png
Issue date: 02/12/1980
From: Beach A, Crossman W, Randy Hall
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19322E363 List:
References
50-382-80-02, 50-382-80-2, IEB-79-02, IEB-79-2, NUDOCS 8003270285
Download: ML19322E366 (6)


See also: IR 05000382/1979002

Text

_

.

.

U. S. NUCLEAR REGULATORY COMMISSION

CFFICE OF INSPECTION AND ENFORCEMENT

>

REGION IV

Report No. 50-382/80-02

Docket No. 50-382

Category A2

Licensee:

Louisiana Fower and Light Company

142 Delaronde Street

New Orleans, Louisiana

70174

Facility Name:

Waterford Steam Electric Station, Unit No. 3

Inspection at:

Waterford Site, Taft, Louisiana

Inspection conducted:

January 29-31 and February 1, 1980

2[/2/80

Inspectors:

~ Reactor Inspector, Projects Section

Date

=__

_-

p(Paragraphs

. C. Stewart,

1, 2, 3, 4, 5 & 8)

O'

  • [/

??'

[ L. D. Gilbert, Reactor Inspector, Engineering Support

Date /'

l'

Secticn (Paragraph 7)

'

/

@

,

-A.

B. Beach, Reactor Inspector, Engineering Support

Date

Section (Paragraph 6)

Approved:

80

m

W. A. Crossman, Chief, Projects Section

Date

d

2-

e

j@

R. E. Hall, Chief, Engineering Support Section

Date

80032702 25

. _ -

-

.

Inspection Summary:

Inspection on January 29-31 and February 1, 1980 (Report No. 50-382/80-02)

,

Areas Inspected: Routine, unannounced inspection of construction activities

related to a follow-up review of in-process welding activities on Reactor

Coolant pressure boundary piping; a follow up on the licensee's response to

IE Bulletin 79-02, Revision 2; procedure review and observation of work

related to care and maintenance of installed safety-related components.

The

inspection involved sixty-five inspector-hours by three NRC inspectors.

Results: No items of noncompliance or deviations were identified.

1

!

,

4

1

4

!

'

.

I

~2-

t

I

- -.

, , . -

.,

. - - .

-.~ . _ _ , . , .

.

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • T. Gerrets, QA Manager
  • B. Brown, QA Engineer
  • C. Chatelain, QA Engineer
  • J. Woods, QA Engineer
  • C. Decareaux, Project Coordinator

D. Lester, Plant Manager

_0ther Personnel

  • J.

Crnich, Site Manager, Ebasco

  • R. Milhiser, Project Superintendent, Ebasco

R. Hartnett, QA Site Supervisor, Ebasco

  • L.

Stinson, Site QA Program Manager, Ebasco

  • J. Britt, Site Manager, Nuclear Installation Services Company (NISCO)

J. Moska, QA Manager, NISCO

W. Barthle, Piping Superintendent, NISCO

J. Ball, Welding Engineer, NISCO

T. Pruitt, Site Auditor, NISCO

The IE inspectors also interviewed other licensee and contractor personnel

including members of the engineering and QA/QC staffs.

  • Denotes those attending the exit interview.

2.

Licensee Action on Previous Inspection Findings

(Open) Interim Construction Deficiency Report (CDR):

" Procedural and Per-

formance Deficiencies in Ultrasonic Testing of Structural Welds Performed

by Industrial Engineering Works," dated January 2, 1980.

The IE inspector

reviewed the status of the progress in the licensee's evaluation of the

extent and magnitude of the deficiencies and the corrective action necessary.

As noted in the Interim Report, the ultrasonic testing (UT) examination

deficiencies involve the welds on the Reactor Coolant pump supports, Reactor

Coolant system pipe stops, pipe whip restraints, pressurizer support, Safety

Injection tank supports and framing over the steam generators.

It is esti-

mated by the licensee that 3000 welds are involved that require individual

review. As of January 28, 1980, the A/E has completed review of the welds

on the framing over the steam generators involving 1022 welds. Approximately

396 full penetration welds can be reduced to partial penetration, thereby,

leaving 626 welds that need UT re-examination.

The A/E is continuing weld

analysis of the remaining support structures.

This matter will be reviewed by the IE inspector during a subsequent site

inspection.

-3-

.

.

(Closed) Infraction (50-382/79-03):

Failure to Follow Approved Drawing -

Mounting / Installation of Class IE 4160 Volt Switchgear.

During this

inspection, the IE inspector reviewed the corrective action implemented

in correcting the original discrepancy in the drawing details and disposition

described by the licensee in their letter, dated April 27, 1979.

The review

by the IE inspector included the review of Nonconformance Report W3-1295,

dated March 20, 1979, which reflects a close out, dared September 24, 1979.

The IE inspector had no further questions regarding this matter.

3.

Safety-Related Components - Procedures - Protection After Installation

During the inspection, the IE inspector reviewed the licensee's subcontactor's

procedures involving the storage, maintenance and protection of safety-related

components after installation.

Procedures and instructions reviewed included

the following:

Ebasco Procedure ASP-IV-19, " Care and Maintenance of Permanent Plant

Items," dated October 10, 1979

Mercury Company Procedures, " Material Receiving Inspection Procedure,"

QCP-3110.1, Revision 1, dated October 19, 1978; " Project Control

Procedure," PCP-2040, dated October 23, 1978; and Construction

Procedure SP.651, " Construction Procedure for Installation of Local

Mounted Instrument Racks and Cabinets," Revision 2, dated September 7,

1978

1

Fischbach & Moore, Inc. Procedure QNP-303W3, " Material and Equipment

Handling, Storage and Maintenance," Revision 1, dated March 14, 1978

Tompkins-Beckwith, Inc. Procedure TBP-46, " Care and Maintenance of

Permanent Plant Items," Revision A, dated May 14, 1979

No items of noncompliance or deviations were identified.

4.

Safety-Related Components - Procedural Implementation Protection After

Installation

In conjunction with a procedure review, the IE inspector conducted an overall

plant walk-thru and records review to ascertain procedural implementation for

the protection and maintenance of safety-related components after installation.

Observations were made on all levels of both the Reactor Containment Building

and Reactor Auxiliary Building, including reactor vessel internals being

installed (core support barrel) and vessel internals stored in containment.

Records reviewed included the following:

"Inplace Monitoring Log," form ASP-IV-19-5, for the period May 31, 1979,

through January 30, 1980

-4-

.

Care and Maintenance Surveillance Reports, File Folder, " Reactor Vessel

Internals," September 10, 1979, through December 28, 1979, including

cleaning water analyses reports

Folders containing Care and Maintenance Audit Reports with contractor

response for the period September through December 1979

No items of noncompliance or deviations were identified.

5.

Site Tour

The IE inspectors walked through various construction and storage areas to

observe construction activities in progress and to inspect the general state

of cleanliness and adherence to housekeeping requirements.

No items of noncompliance or deviations were identified.

6.

IE Bulletin 79-02, Revision 2

The IE inspector observed activit'e. and reviewed records for those base

plates addressed by IE Bulletin 79-02, Revision 2, " Pipe Support Base

Plate Designs Using Concrete Expansion Anchor Bolts." Ebasco Specification

No. LOU 1564.468, " Drilled-in Expansion Type Anchors in Concrete for Category

I Structures," established the installation, inspection, and testing require-

ments for the use of concrete expansion anchors at the site.

Procedure TBP-33, " Procedure for Inspecting Drilled-in Expansion Type Anchors

in Seismic Class 1 Concrete," established the torquing verification check of

all seismic Class 1 concrete expansion anchor bolts.

In addition, one out of

every one-hundred concrete expansion anchor bolts tested should also be tension

tested.

Should a failure occur, three additional anchor bolts would be tested,

and if any one of these bolts failed to meet the required tensile loads, then

the entire group of the one-hundred anchor bolts would be tested.

Procedural requirements are as follows:

Minimum

Bolt Size

Embedment

Torque (ft-lbs)

Tension (lbs)

3/8"

3"

30-40

1455

1/2"

5"90-100

3795

5/8"

6"

150-170

5060

3/4"

7"

185-210

6758

1"

7"

325-375

8602

l

I

-5-

.

.

A field inspection of several installed base plates and a general review of

records for hangers SIRR-981, FSRR-265, and EARR-7 indicated the requirements

of IE Bulletin 79-02, Revision 2 were being met.

Additional review will be

required during a subsequent inspection concerning the design modifications

and the resulting addition of stiffener plates to include the effects of the

base plate flexibility.

No items of noncompliance or deviations were identified.

7.

Reactor Coolant Loop Piping

The IE inspector observed welding being accomplished on the four pipe welds

that connect the No. 1 steam generator to Reactor Coolant pumps No. lA and

IB.

The four welds, identified as P3Wl, P4Wl, P7W1 and P8W1 on NISCO Drawing

3015-003, were being welded with the shielded metal-are process.

The welders

were using electrode type E7018 for welding P3W1 and P7W1 and electrode type

E308-16 for welding P4W1 and P8W1 as specified in weld procedure specification

(WPS) 10.1.14, Revision E and WPS 80.3.2, Revision A, respectively.

In addition to observing welding activities, the IE inspector observed post-

weld heat treatment of weld P16W2, a, carbon steel weldment in the intermediate

pipe leg between steam generator No. 2 and Reactor Coolant pump No. 2B, for

compliance with NISCO Procedure E3016-1, Revision B and Section III NB of the

ASME B&PV Code.

Observations by the IE inspector included spacing of the

thermocouples, placement of the heating pads, and monitoring of the controller-

recorder temperatures.

The in-process testing of two welders was observed by the IE inspector.

The

g

welders were using electrode type E7018 and welding with the pipe in a 45

position as required for qualification to NISCO WPS 10.1.14 in accordance

with WQT-187, Revision C.

Bend test specimens were removed from the test

welds and evaluated by the test examiner for compliance with Section IX of

the ASME B&PV Code and the acceptable results were confirmed by the IE

inspector.

No items of noncompliance or deviations were identified.

8.

Exit Interview

The IE inspectors met with licensee representatives (denoted in paragraph

1) at the conclusion of the inspection on February 1, 1980.

The IE

inspectors summarized the purpose and the scope of the inspection and the

findings.

-6-