E g '.v...f RECORD OF TELEPH0fiE CONVERSATI0ft Wednesday, August 15, 1979 9:00 a.m. - 9:10 a.m.
H. Brent Clayton NRC NRR-DPM-Quality Assurance Branch 492-7741 Brent was offering some ideas on establishing a startup test benchma-k for comparison with the TMI-2 startup test program.
The Standard Review Plan, Section 14.2, in Acceptance Criteria #10 mandates that a licensee must schedule a minimum of nine months for preocerational testing (before fuel loading) and a minimum of three months for startuo testirig (after fuel loading).
TMI-2's test program was not completed by December 31, 1978; the last tests were completed on January 2, 1979.
Dick Keimig, IE-Region I, 8-488-1252, has more information on TMI-2 test program. Also Don Haverkamp, IE-Region I.
Brent felt Crystal River 3 was a good recent example of a B&W startup test program.
Fuel load 12/4/76 Initial Criticality 1/14/77 Comercial Operation 3/13/77 Finish startup tests 4/26/77 Chris Nelson, NRR, Division of Operating Reactors, x-27435, is the Licensing Project Manager for Pystal River 3.
I asked Brent if he knew of any plants that had either: a) declared commercial operation before completing startup tests or b) declared commercial operation after completing startup tests.
D.C. Cook 2 declared comercial operation 7/1/78 and to date has not completed test program.
Brent believes there are examples (bcaiga Tttt=t) of units declaring connercial operation before test completion.
C+= L To prepare a' schedule showing the time each test was performed, probably wculd have to review Monthly Operating Reports.
The Startup Test Reports do not generally show dates for test completien.
8LO b l
800118 0 l
l Record of Telephcne Conversation 2
August 15, 1979 TMI-2's Startup Test Reports are:
12/28/78 Initial Report (Fiche #7901050143)
(9 months after initial criticality per Section 6.9.1.3 of TMI-2 Tech Specs, Operating License DPR-73) Report noted that " Test procedures for power ascension were not completed by time report written."
3/23/79 Supp. #1 (Fiche #7903290162) 6/11/79 Supp. #2 (Fiche #7906260455)
Notes that Final Report to be issued when manpower available.
R. L. VanJenberg
.