Preparation & Submittal of Detailed Responses to Draft Suppl to Fes Cannot Be Completed Before 790418 Deadline. Detailed Responses Will Be Forwarded within 2 Weeks
ML19322A321
Person / Time
Site: 05000471
Issue date: 04/17/1979
From: Rhonda Butler, Mchugh G
BOSTON EDISON CO.
To: Regan W
Office of Nuclear Reactor Regulation
References
NUDOCS 7904240449
Download: ML19322A321 (2)


Text

.

COOTON ELCON CIMPANY 0:w. u c t m ica c o3 Ca n .7:n te x rv

h. soevo! ' U = s a.M u s.tre 0 219 9

.o..=......

. . ... ....... o..... .w, April 17,1979 William H. Regan, Jr. , Chief Environmental Projects Branch #2 Division of Site Safety and Environmental Analysis U.S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Sir:

In your letter of April 10, 1979, you requested by April 18 our responses to comments submitted by reviewers of the Draft Supplement to the Final Environmental Statement for the Pilgrim Nuclear Power Station Unit #2.

The short time available does not permit us to prepare and submit de-tailed responses by the April 18 deadline.

We believe it is in order for us to prepare and submit detailed responses for the following reasons:

1. It is clear that the NRC Staff has done a detailed, compre-hensive, independent evaluation of alternative sites. There is no question that the efforts of th: NRC Staff during the past year satisfy the requirements of the Nat1onal Environmental Policy Act.
2. Some of the reviewers cannents were directed toward actions of the applicants. Since these comments are unfounded, we are obliged to respond and set the record straight.
3. Some of the comments of the Attorney General of the Commonwealth of Massachusetts attempt to raise issues which have no connection with the question of alternative sites, which is the sole subject matter of the Draft Supplement. Furthermore, some of the comments of the Attorney General appear to be based upon novel interpre-tations of NRC case law or upon wording which, although it did appear in the cited cases, is clearly quoted out of context.

790424gi]qq I s

i CQ3 TON EOCON COMPANY l

4 Wm. Regan, Jr.

Page 2 April 17, 1979 We intend to prepare and submit detailed responses to cocinents within approximately two weeks. This will provide all parties with sufficient time to review our responses well in advance of hearings.

A Very truly yours, ro" gpB ;