Reports on Status of Solid Waste Handling Sys.Structural Work & Installation of Pump,Piping & Instrumentation Are Completed.Preoperational Test Will Be Completed by Dec 1978. Control Panel Will Be Delivered by 790115
ML19322A188
Person / Time
Site: Dresden 
Issue date: 12/19/1978
From: Turvak M
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 7901040230
Download: ML19322A188 (1)


Text

- -

-~

l N

O3 C:mm:nw:dth Edison ons rarst National Plaza Cb_ctgo Ilknois p/f

. Address Reply to: Post Office Box 767 Chicago. Ilknois 60690 December 19, 1978 Mr. James G. Keppler,' D,irector Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Subject:

Dresden Station Unit 1 Solid Waste liandling System NRC Docket No. 50-10 Reference (a) :

M. S. Turbak letter to J. G. Keppler dated March 20, 1978.

Dear Mr. Keppler:

4 Reference (a) indicated that b'ased on projected' delivery dates of the ifVAC equipment we anticipated completion of the Dresden Unit 1 solid waste handling system in the last quarter of 1978.

The structural work and installation of pumps, piping, and instrumentation are completed, pre-opgrational testing is currently underway and expected to be finished by the end of December, 1978.

At this time, the liVAC control panel has not been delivered.

The control panel delivery date to the site is now expected the week of January 15, 1979.

Therefore, pumps and related instrumentation will be operational by the end of the year.

Ilowever, the Solid Waste liandling System will be operable in the first quarter of 1979 when the IIVAC equipment becomes operable.

please address any questions regarding this matter to this office.

Very truly yours, M. S. Turb.

Nuclear Licensing Administrator Boiling Water Reactors 790104 023 0 DEC 301978