.TC 50-E&?
OL ConSum8IS
=mo
"~
Power Company Midland Project:
P.O. Box 1963, Mksland, Michigan 48640. Area Code $17 631-0951 July 3,
1980 James G.
Kopplcr, Regional Director Offico of Inspection & Enforcement, Region III U.S.
Nuclear Regulatory Commission 799 Roosevcit Road Glen Ellyn, IL 60137 MIDLAND PROJECT GWO 7020 REVISED PROJECT MILESTONES File:
0652.1 Serial: CSM-0298 UFI: 53*S4 We have completed our oval ua tion of the Midland Project Schedule and have established the following revised compl e tion dates:
Uni t #2 Fuel Load July, 1983 Unit #2 Commercial -
December, 1983 Unit #1 Fuel Load December, 1983 Unit #1 Commercial Steam Operation July, 1984 The. integrated 2-unit start up program has been retained.
The September, 1980 NRC Yellowhook update transmittal from CPCo will reficct revised miles tono da tos based on the above completion dates.
P1caso ny comments or questions.
D.B.
Miller Si te Manager CC:
W.H.
Lovelaco Office of Management & Program Analysis DhDO l-//-D PM Terc 8007280 09i
[