Corrects Requesting Updated & Complete Schedule of Safety Review.Correct Fuel Load Date Is 810831
ML19320C296
Person / Time
Site: Grand Gulf  
Issue date: 05/14/1980
From: Dale L
MISSISSIPPI POWER & LIGHT CO.
To: Baer R
Office of Nuclear Reactor Regulation
Shared Package
ML19320C292 List:
References
AECM-80-79, NUDOCS 8007160617
Download: ML19320C296 (1)


Text

.

hf MISSISSIPPI POWER & LIGHT COMPANY Helping Build Mississippi E

P. O. B O X 164 0. J A C K S O N, MIS SIS SIP PI 3 9 2 0 5 CORRECTED COPY PRODUCTION QCFARTMENT May 14, 1980 Mr. Robert L. Baer, Chief Light Water Reactors Branch No. 2 Division of Project Management U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Baer:

SUBJECT:

Grand Gulf Nuclear Station Units 1 and 2 a

Docket Nos. 50-416 and 50-417 File 0260/0277/L-860.0/0440 Request for Licensing Review Schedule AECM-80/79 As you are aware, we have recently rescheduled our fuel load date for Unit 1 to August' 31, 1981.

In order to expedite our licensing activities, please provide us with the most up-to-date and complete schedule for the NRC Safety Review of Grand Gulf Unit 1.

Thank you,

  • : t$

ff J$

L. F. Dale Nuclear Project Manager MRK/JDR:lm