Requests Extension of Comment Period on NUREG-0577 Until 800915,due to Other Work Efforts.Requests Notification Only If Extension Found Unacceptable
ML19320C015
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 07/03/1980
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Snaider R
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-12, REF-GTECI-ES, RTR-NUREG-0577, RTR-NUREG-577, TASK-A-12, TASK-OR TAC-10139, TAC-7187, NUDOCS 8007150648
Download: ML19320C015 (1)


Text

EiY)( lt O

Wisconsin Electnc ecw com.a 231 W. MICHIGAN P.O. BOX 2046. MILWAUKEE. WI 53201 July 3, 1980 Mr. Richard Snaider Generic Issues Branch U. S. NUCLEAR REGULATORY COMMISSION Washington, D. C. 20555

Dear Mr. Snaider:

NUREG-0577 Mr. D. Eisenhut's letter of May 19, 1980, transmittec~

the subject report and requested that comments be forwarded to NRC by July 7, 1980. In NUREG-0577, Point Beach Nuclear Plant is categorized as a Class I plant and, thus, we have an interest in performing a detailed and thorough review of this report.

Unfortunately, due to other work efforts, we have not been able to complete our raview of NUREG-0577 within the allocated time period. Therefore, we request that the comment period be extended to September 15, 1980, which should be sufficient for completion of our review. Assuming no additional correspondence on this subject, we will proceed under the assumption that the comment period time extension is acceptablei Very truly yours, 9/

l'{L. .

/

C. W. Fay, Director Nuclear Power Department Copy to: Office of Inspection and Enforcement Region III X6o/