Responds to NRC Re Violations Noted in Insp Rept 50-313/74-15.Corrective Actions:Discrepancies in Jumper & Bypass Log Procedures Corrected.Training Sessions for Maint & Operations Personnel Will Stress Adherence to Procedure
ML19320A081
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 01/17/1975
From: Cavanaugh W
ARKANSAS POWER & LIGHT CO.
To: Moseley N
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19320A074 List:
References
NUDOCS 8004140691
Download: ML19320A081 (2)


Text

..

~

O,.

[7

  • l

)

  • [J (U) n et or n a austa annansas g

ARK ANS AS POWER G LIGHT COMPANY January 17, 1975 United States Atomic Energy Commission Directorate of Regulatory Operations Region II 230 Peachtree Street, N.W., Suite 818 Atlanta, Georgia 30303 Attention:

Mr. Norman C. Moseley Director

Subject:

Arkansas Power & Light Company Arkansas Nuclear One - Unit 1 License No. DPR-51 Insp. Rept. RO:II 50-313/74-15 Gentlemen:

\\

We have reviewed your letter of January 6, 1975 and the following is our response to the apparent violation cited in that report. This response details the violation, corrective action and results achieved, steps taken to avoid further violation and the date when compliance will be achieved.

The apparent violation consisted of the lack of completion of a page of the Jumper and Bypass Log as required by Procedure 1005.04, " Control and Use of Jumpers and Bypasses". The particular discrepancies noted were corrected immediately. To assure that no further violations of this type occur, the procedure for the use of jumpers and bypasses was discussed in detail with supervisory personnel. The need for strict adherence to the procedure was emphasized. Also, a training session is being planned for non-supervisory personnel.

Sessions for affected operations personnel are to be complete by March 1,1975. Sessions for affected maintenance and instrument personnel are to be completed by February 1, 1975. The details, as well as the importance of strict adherence to the procedure, is to be emphasized.

We feel that this effort should be quite adequate to assure no further violations of this nature.

j Si erely, PDR gy! SENT TO:

gA1^ '

wa-ItSICs n

TIC" William Cavanaugh III

[

\\

Manager, Nuclear Service WC:mb 8004140f1 h usuaea uioote sours urit ries sysreu v x

.vi~o. i~vesraa ow~eo

O f4 3

=

e i

Ltr to Arkansas Power and Light Company fm N. C. Moseley and R Inspe ti n Report No. 50-313/74-15 dated JM 6 SS DISTRIBUTION:

H. D. Thornburg, RO p_

A' AJ HQ (5)

Regulatory Standards Directorate of Licensing (13)

DR Central Files

  • PDR
  • NSIC
  • State
  • To be dispatched at a later date

)

i

,...,. _ _ _ _ _