UCENSEE EVENT REF 1T 1

CONTROL BLOCK:l l

l l

l l

l (MAASE MIMfT ALL M NTWN]

1 6

"MN'

'#4' tce~se Nuuena l AIRI A IRlw I t I lo 101-10 lo lo lo 101-10 lo I 14IiliIsIil lojal 7 89 14 15 25 28 30 31 32 ryPE e"En$

cAftcony cocutt Nuusta tVENT OAft HEPORT DAtt O 1 CONT l l

l

[L_]

lL l 101Sl0l-1013lf13I lo l( 10 lE l T 17 I lo ll l o l l 1717 l 7 8 57 58 59 60 61 68 69 74 75 30 l

EVENT DESCRIPTION HE l b sTraarr-STATE Powet boo'if P). A V.Emerae beLDIred 6 wa FAN W As Foo 94O To Ett 7 89 80 BE I wouwm. As mm, w rawa semaus. as-sit eum To tean ewa ss.

I 7 89 80 EE I usum weues %.u. s tocToe suicain wat %s Wm-\\ A me \\s.

I 7 89 80 20 ! k itMWs4T 5 YSTim W e W Ait.Aa L C % C Put nat.c. T 4 W 15 MOT A %.EPET1 Tid I

7 89 80 EE I o o=e..wx. L h. wu e_ w.o we amu. To rwe wuoen. voe esam.

I Eo'a*

cc"o'n'

^

COMPONENT COCE Mmuracn a vaA 15 IB I [.5.]

16 It lo IWis I e.1

[}_J l e.1 s I r. Is i LN_J O

7 89 10 11 12 17 43 44 47 48 CAUSE DESCAIPTION l k (s.Ligast $GCTit.w bmf Amy' McTolt. TAgteo Dot To \\ sonsegator t.,0 6 AAC 4T i e d 8

7 89 80 0

1 % =.,:w t %xot b an.ie u. AvT.:.s. m u woe u waan wo esvoa.nss By I

7 89 80 l Tug h @ cod,kwe QtAcqy y qgggety, hg.,1, peect pa, 3 w g t t, gavg T gg Stggay($ l 0

g,%TC*

  • . H 4Qc w T sc.ww. outs.,,,,gog, 89

'd 80 stafus

% POwtA OTHER Status CrScovtav CGCOVERY OtSCRIPTcN Isl lilolol I wn I

Lb.J l

wx I

1 7 8 9

10 12 13 44 45 46 80 a'atrYs'c'o or NEAst aucuNT or actmiv tocArcs or netsass 13J 1.1) 1 l

I 12 l

7 8 3

10 11 44 45 80 PEASONNEL EXPOSURES Nuusen type casca.PfcN i

101olol L4J l

9A I

7 89 11 12 13 80 PERSONNEL INJURIES NuustR DEsCRipTON lololol I

aw I

1 7 89 11 12 80 OFFSITE CONSEQUENCES EU l NA i

7 89 80 LOSS OR DAMAGE TO FAC:UTY tvPE DESCRepfCN

[pgj l

MA i

I-7 89 10 80 PUBLICITY 17 QA 7 89 80 g o 04110 [J7 ADDITIONAL FACTORS I

wA i

09 80 -

7 89 be C.

beou

, san, Soi f rtt-44 %

NiuE:

GPO set.egy

L-Reportable Occurrence P.cport No.

50--313/77-13 2.

Report Date: July 1, 1977 3.

Occurrence Date:

June 2, 1977 4

Facility:

Arkansas Nuclear One-llnit 1 Russellville, Arkansas 72801 5.

Identification of Occurrence:

The failure of a Reactor Building cooling fan which is a condition leading to operation in a degraded mode pemitted by a limiting condition for operation (Technical Specification 3.3.4).

6.

Conditions Prior to Occurrence:

, Steady-State Power y

Reactor Power 2568 MWth Hot Standby Net Output 805 MWe Cold Shutdown Percent of Full Power 100 %

Refueling Shutdown load Changes During Routine Power Operation D

Routine Startup Operation Routine Shutdown

~

Operation Other (specify) 7.

Description of Occurrence:

At 2159 hours0.025 days <br />0.6 hours <br />0.00357 weeks <br />8.214995e-4 months <br /> on June 2,1977, Feeder Breaker B5-512 opened to Load Center B5, which supplies power to Reactor Building Cooling Fans VSFM-1A 618. An investigation and meggering of both fan motors indicated grounded phase windings in VSFM-1A after which Load Center B5 was re-energized. The tripping of Breaker B5-512 indicated that selective tripping did not occur since Breaker 52-523 (feeder breaker to VSFM-1A) should have tripped.

V

,n,-~

v - -

~

m.

C\\

Reportabic Occurrence Report No.

50-313/77-13 8.

Designation of Apparent Cause of Occurrence:

Design Proc' dure e

Manufacture Unusual Service Condition Including Environmental Installation /

Construction Component Failure X

(See Failure Data)

Operator Cther (specify)

X The motor bearings had insufficient lubrication.

9.

Analysis of Occurrence:

Since a safety analysis was performed for operation with less than 4 RB cooling fans and the subsequently approved technical specification changes allow 2-cooling units to be operable and powered from independent busses, there was no hazard to the health and safety of the public.

e d

b i

t r

i

%._/

q l

l

+

l

-. -..- - 1

m_

V Reportable Occurrence Report No. 50-313/77-13 10.

Corrective Action:

The motor was removed and shipped to the vendor. (Reliance Electric

-Company) to be rebuilt. The remaining 3 fan unit's bearings were lubricated and will be placed on a more frequent lubrication schedule.

. The bearings in at least one of the redundant fans will be inspected by the end of the next refueling outage. A breaker test was performed on Breaker 52-523 which indicated that the trip had drifted high. A Preventive Maintenance Program is being established to test all vital 480 volt circuit breakers and calibrate all overcurrent relays.

N 11.

Failure Data:

Fan Motor: VSFM-1A, 480 volt, 125 HP, 1800 RPM, 60 cycle, 3 phase induction motor, fram design 7DB-5003, Reliance Electric Company.

Circuit Breaker: 52-523, 480 volt, 225 AMP ACB, Trip Coil Model OD-5, ITE Manufacturer.

G V

_