TOLEDO EDISON LowtLL E. Act u..... n..,
14191 259-5242 June 7,1974 Docket No. 50-346 Dr. Donald F. Knuth, Director Directorate of Regulatory Operations Office of Regulation U. S. Atomic Energy Commission Washington, D. C.
20245
Dear Dr. Knuth:
This letter is submitted as an Interim Report regarding the Davis-Besse Nuclear Power Station Unit No. I high pressure injection pump motor starting torque deficiency related by telecon to Mr. W. E. Vetter, Directorate of Regulatory Operations, Region III on April 25,1974.
The above motors have been returned to Westinghouse for test and repair as may be necessary. Initial tests have been performed and limited repair work initiated. A defm' itiw report of the deficiency, analysis of the safety implications, and the corrective action being taken will be submitted to yont office in accord with 10CFR Part 50.55 upon completion of our study of this problem.
Yours very truly, cc:
J. G. Keppler, Regional Director Director of Regulatory Operations Region 11I b
THE TOLEDO EDISCN COMPANY EDISON PLAZA 300 MAO!SCN AVENUE TCLECO. CHIO 43652 8001310$3[