ML19318D244

From kanterella
Jump to navigation Jump to search
Advises That Emergency Notification Sys Telephone Does Not Require Onsite Auxiliary Power Supply,In Response to IE Bulletin 80-15.Test to Verify Independent Power Will Be Conducted within Next 30 Days,During Scheduled Power Outage
ML19318D244
Person / Time
Site: West Valley Demonstration Project
Issue date: 06/26/1980
From: Duckworth J
EMVNFWV, NUCLEAR FUEL SERVICES, INC.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
1-80-066, 1-80-66, IEB-80-15, NUDOCS 8007080246
Download: ML19318D244 (1)


Text

_ _ _ _ __ . - _ _ _ _ . - _

P ev Nuclear Fuel Services, Inc. P.O. Box 124

  • A Subsidiary of Getty Oil Company (716) 942-323f l l

l June 26, 1980 1-80-066 l l

l

- Mr. Boyce H. Grier, Director US Nuclear Regulatory Comission Region 1 631 Park Avenue King of Prussia, PA 19406 Re: Docket 50-201 IE Bulletin 89-15

Dear Mr. Grier:

In response to your IE Bulletin No. 8815, we have determined by direct inspection with a representative of the Iroquois Telephone Company that the Emergency Notification System (ENS) telephone at our West Valley plant is supplied with power by the telephone company (and does not receive any 120V AC from the plant powerconfirming e supply does not require an ,on-site auxiliary power supply.

At our next scheduled power outage and test of the emergency diesel generator (EDG), we will conduct a test of the ENS to verify that it is independent of on-site power. This test will be conducted within the next thirty days.

Very tguly,yours,

[

J. P. Duckworth General Manager JPD: bon cc: NRC Office of Inspection & Enforcement Washingto,n, DC 20555 NRC Document Management Branch , y 4 Washington, DC 20555 fFg b

\'\