ML19318B760

From kanterella
Jump to navigation Jump to search
Lists Ltrs Incorporating Detailed Electrical, Instrumentation & Control Drawings Re Facility Design.Action Is Taken in Conformance W/Nrc PM Operating Procedure 208, Revision 1, Submittal of Supplementary Detailed Data
ML19318B760
Person / Time
Site: Comanche Peak  
Issue date: 06/06/1980
From: Burwell S
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
NUDOCS 8006300020
Download: ML19318B760 (1)


Text

,

fW'%es "A

UNITED STATES 8"

7.

NUCLEAR REGULATORY COMMISSION WASHINGTON D. C. 20555

%,...../

D.ocket Nos. 50-445 JUN 0 61980 and 50-446 MEMORANDUM FOR: Central Files R.

FROM:

S. Burwell, Project' Manager, Licensing Branch No. 2, DL

SUBJECT:

FILING UF DETAILED ELECTRICAL, INSTRUMENTATION AND CONTROL (EI&C) DRAWINGS The Texas Utilities Generating Company (TUGCO) has submitted detailed electrical, instrumentation and control drawings relating to the design of the Comanche Peak Steam Electric Station, Units 1 and 2, as enclosures to the letters identified below:

Date NRC Accession No.

From (TUGCO) to NRC February 27, 1978 780610017 H. C. Schmidt to E. G. Case August 27, 1979 7909110086 R. J. Gary to R. L. Baer December 12, 1979 7912270170 R. J. Gary to R. L. Baer February 28, 1980 8003050292 R. J. Gary to R. L. Baer March 12, 1980 8003180389 R. J. Gary to R. L. Baer April 18, 1980 8004290521 R. J. Gary to H. R. Denton April 22, 1980 8004290634 R. J. Gary to H. R. Denton April 22, 1980 8004300526 R. J. Gary to H. R. Denton These drawings were placed in the Central Files at the NRC Headquarters, 7920 Norfolk Avenue, Bethesda, Maryland.

Due to their nature these supplementary detailed data are not being placed routinely in the Public Document Rooms.

e This action is taken in conformance with the NRC's PM Operating Procedure 208, Revision 1, " Submittal of Supplementary Detailed Data," May 23, 1979.

S /b /Y.a-rt S. B. Burwell, Project Manager Licensing Branch No. 2 Division of Licensing