Forwards Final Deficiency Rept Re Defective Westinghouse Switches
ML19318B698
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 06/13/1980
From: Fahrner W
DETROIT EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19318B699 List:
References
EF2-49-015, EF2-49-15, NUDOCS 8006270330
Download: ML19318B698 (1)


Text

O I

i 2 coo seco o A June 13, 1980 l%Q ygyg"ves.

de22s EF2-49,015 Mr. James C. Keppler Regional Director Directorate of Regulatory Operations Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 Subj ect:

10CFR50.55(e) Item on Defective Westinghouse Switches.

Dear Mr. Keppler:

This letter is submitted as Detroit Edison's final report on the 10CFR50.

55(e) item on defective Westinghouse Switches.

On December 7, 1979 Detroit Edison's Mr. H.A. Walker telephoned Mr. F.J.

Jablonski of NRC Region III to report on defective Westinghouse Switches in distribution cabinets used to distribute power for plant instrumentation and control at the Fermi 2 Site. These switches were manufactured by West-inghouse Electric Corporation and furnished to Detroit Edison by the Harlo Corporation.

Edison Engineering has completed their evaluation of this deficiency. The attached report includes a description of the deficiency, and the correc-tive action taken. Corrective action will be completed in accordance with the construction.chedule.

If you have any questions regarding this matter, please contact Mr. H.A.

Walker, Supervisor - Construction Quality Assurance.

Sincerely, l

W.J. Fahrner, Manager Enrico Fermi 2 WJF/ HAW /pn ec:

Mr. Victor Stello, Jr., Director Office of Inspection and Enforcement Division'of Reactor Inspection Programs U.S. Nuclear Regulatory Commission Washington D.C.

20555 Mr. Bruce Little, Resident Inspector Soli Office of Inspection and Enforcement 5

Enrico Fermi 2 Construction Site

/

Newport, Michigan 48166

//[

~