ML19318B003

From kanterella
Jump to navigation Jump to search
Forwards LER 80-087/03L-0
Date released: 11/28/2019 Download: ML19318B003


LER 80-087/03L-0:on 800528,during Surveillance Procedure HNP-2-3154,reactor Pressure Vessel Level Instrument (LPCI) Ft&C on 2B21-NO31B,Switch 4,had Double Actuation.Caused by Slipped Magnets on Pointer Shaft Due to Corrosion
ML19318B005
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 06/19/1980
From: Nix R
GEORGIA POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19318B005 (2)
Forwards LER 80-087/03L-0
ML19318B002
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 06/19/1980
From: Manry M
GEORGIA POWER CO.
To: OREILLY J P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19318B002 (1)