O~tober 15, 2019 NRC3-19-Q002 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC. *20555-0001
Reference:
Fermi 3 NRC Docket No.52-033 NRC License No. NPF-95 DTE Energy One Energy Plaza, Detroit, Ml 4822~1279 DTE 10 CFR 50.59 1 O CFR 52 Appendix E 10 CFR 52.3
Subject:
DTE Electric Company Submittal of Fermi 3 Periodic Reports This submittal provides periodic Fermi 3 reports as *required by NRC regulations and license conditions for a Part'52 combined license holder. This submittal provides the following reports:
Semi-Annual Departures Report :
$emi-Annual Changes,. Tests and Experiments Report Semi-Annual Schedule for Implementation of Operational Programs and other License Conditions Report Annual Final Safety Analysis Report* (FSAR) Update
- Semi-Annual Departures Report. In accordance with Sections X.8.1 and X.8.3.b. of the Economic Simplified Boiling Water Reactor (ESBWR) Design Certification Rule (1 O CFR 52, Appendix E), holders of combined licenses that reference Appendix E are required to submit a
. semi-annual report to the NRC containing a brief description of any plant-specific departures from the Desigf"! Contr9l Document (DCD), including a summary of the evaluation of each departure. During the period from.April 18, 2019 to. October 15, 2019, there were no plant-
.specific departures from the ESBWR DCD for Fermi 3.
Semi-Annual Changes, Tests, and Experiments Report In accordance with 1 O CFR 50.59(d}(2), holders of combined licenses are required to submit a report containing a brief description of any changes, Jests and experiments, and summary of the evaluation of each.
This report is required to be submitted at intervals not to exceeidr,pix months until the NRC makes its findings undw 1 O CFR 52.103(g). During the period Jrom April 18, 2019 to October 15, 201 ~. then, were no changes,* tes{s or experiments made pursuant to 1 O CFR 50.59(c).
\\.
. *}) 0 q 5
\\
\\
,Jt((.
\\
I
USNRC NRC3-19-0002 Page2 Semi-Annual Schedule Update for Implementation of Operational Programs and Other License Conditions. The U.S. Nuclear Regulatory Commission (NRG) issued Combined License (COL) NPF-95 to DTE Electric Company (DTE), pursuant to Title 1 O of the Code of Federal Regulations (10 CFR) Section 52.97, "Issuance of combined licenses," on May 1, 2015.
By Reference 2, DTE submitted a delineated schedule update per License Condition 2.D.(11) of the Fermi 3 COL for the following:
A schedule for implementation of the operational programs listed in Final Safety Analysis Report Table 13.4-201, including the associated date for initial loading of fuel.
A schedule for implementation for the license conditions listed in COL Section 2.D.(11 )(a) and (b).
In accordance with License Condition 2.D.(11 ), this schedule is to be updated every six months until 12 months before scheduled fuel loading. During the period from April 18, 2019 to October 15, 2019, there were no schedule updates. The scheduled implementation dates for the operational programs remain as To Be, Determined" (TBD).
Annual FSAR Update. 10 CFR 50.71 (e)(3)(iii) requires that the FSAR filed as part of the COL Application be updated annually until the Commission makes the finding under 1 O CFR
, 52.103(g). The most recent FSAR update was submitted on October 22, 2018. No FSAR information has been revised, deleted, or added since the last submittal. Therefore, the previously submitted FSAR continues to be current.
If you have any questions, or need additional information, please contact me at (313) 235-0443.
Cc:
Sincerely, M.LtK~
Michael K. Brandon, Manager Nuclear Development - Licensing DTE Electric Company George Wunder, NRG Fermi 3 Project Manager Fermi 2 Resident Inspector Ho Nieh, Director, NRC Office of Nuclear Reactor Regulation NRG Region Ill Regional Administrator NRG Region II Regional Administrator Supervisor, Electric Operators, Michigan Public Service Commission Michigan Department of Environmental Quality OWMRP, Radiological Protection Section Craig D. Sly, Dominion Energy, Inc.
Lisa Schichlein, General Electric Art Zaremba, Duke Energy Steve Franzon-e, Florida Power and Light
\\