AECM-80-129, Forwards Third Interim Deficiency Rept Re Failure to Provide Qualified Instrumentation in safety-related Sys.Final Rept Will Be Submitted by 810110
| ML19312E980 | |
| Person / Time | |
|---|---|
| Site: | Grand Gulf |
| Issue date: | 06/13/1980 |
| From: | Mcgaughy J MISSISSIPPI POWER & LIGHT CO. |
| To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| Shared Package | |
| ML19312E981 | List: |
| References | |
| AECM-80-129, NUDOCS 8006180287 | |
| Download: ML19312E980 (2) | |
Text
.
MISSISSIPPI POWER & LIGHT COMPANY Helping Build Mississippi P. O. B O X 164 0. J A C K S O N MIS SIS SIP PI 3 9 2 0 5 June 13, 1980 PRODUCTICN DEPARTMENT Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Region II 101 Mar tetta Street, NW, Suite 3100 Atlanta, Georgia 30303 Attention:
Mr. J. P. O'Reilly, Director
Dear Mr. O'Reilly:
SUBJECT:
Grand Gulf Nuclear Station j
Units 1 and 2 Docket Nos.
50-416/417 File 0260/15526 PRD-79/21, Interim Report #3 Failure to Provide Qualified Instrumentation in Safety Related Systems AECM-80/129 On December 5, 1979, Mississippi Power & Light Company notified Mr. J. K. Rausch of your office of a potentially reportable deficiency at the Grand Gulf Nuclear Station construction site. The deficiency concerns General Electric's failure to provide seismically and environmentally qualified instruments for use in nuclear safety systems in the Balance af Plant (BOP) Power Generation Control Complex (PCCC).
We have determined that this matter constitutes a reportable condition under 10CFR50.55(e).
Furthermore, we have concluded that this condition is also required to be reported under 10CFR21. This letter to you, with Interim Report Number 3 attachment and previous submittals constitutes our required reporting of this matter under both 10CFR50.55(e) and 10CFR21 for the information which is now availabic.
Mr. W. E. Edge of MP&L notified Mr. F. Cantrell of your office by telephone i
of the reportability under 10CFR21 on June 12, 1980, and confirmed 10CFR50.55(e) time requirements apply.
A final report with corrective actions will be submitted to you by January 10, 1981.
Yours trul>],
y[s.
(
THIS DOCUMENT CONTAINS POOR QUAUTY PAGES J. P. McGaugby, Jr.
Assistant Vice President Nuclear Proudction WEE:lb
Attachment:
(Continued on following page) 80061802.M $
Member Middle South Utilities System
MISSISSIPPI POWER O LIGHT COMPANY j
Office of Inspection & Enforcement AECM-80/129 U. S. Nuclear Regulatory Commission Page 2
Attachment:
Interim Report #3 cc:
Mr. N. L. Stampicy Mr. R. B. McGehee Mr. T. B. Conner File Mr. Victor Stello,Jr., Director (w/3 copies + attachments)
Division of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
20555 i
--