Forwards Bimonthly Status Rept of Environ License Amends. Updates 800206 Rept
ML19312E395
Person / Time
Issue date: 04/04/1980
From: Lear G
Office of Nuclear Reactor Regulation
To: Muller D
Office of Nuclear Reactor Regulation
References
NUDOCS 8006040368
Download: ML19312E395 (8)


Text

?.

$WNY fh DISTRIBUTION Central Files NRR Reading ET Reading ESB Reading April 4,1980 Glear TCain MEMORANDUM FOR:

Daniel R. Muller, Acting Director Division of Site Safety and Environmental Analysis THRU:

Malcolm L. Ernst. Assistant Director for Environmental Technology, DSE BROM:

George Lear, Chief Environmental Specialists Branch, DSE

SUBJECT:

STATUS REPORT OF ENVIRONMENTAL LICENSE AMENDMENTS Enclosed is the bimonthly status report of DOR license amendments. Since our last report of February 6,1980, we have completed 5 TAC requests while 4 new requests came in. Currently a total of twenty requests is in for review.

License amendments were issued by DOR for two completed TAC's.

George Lear, Chief Environmental Specialists Branch Division of Site Safety and Environmental Analysis Enclosure t Status Report

.M cc:

M. Ernst

^^;p R. Ballard G. Knighton 1

ESB Branch Members DOR BC's

Contact:

T. D. Cain, DSE X28S68

/\\

?v 8006049 U.,M.

.......:DSE E :ESB T:ESB DSE:ET:E B

.. T........

DS omce>

,,,,,,a o rt,,,,,,, G L,e a r.. %/

_,... p t....

sunumi)h.. T,D@,,,,,1 c,,f

...../. l... /.80 4/4/80 4/ /80

..../..y. / 80 4

4 i

,y, y......

ESB WORK SCHEDULE TECH SPEC (NON-RAD ENVIRON) CHANGES licensee Date of RAI

Response

ESB Response TAC No.

TAC Receipt Issued Received to 00R Remarks /Amm. Ident./ Reviewer 7309 2/15/78 6/29/79 C Complete / Robinson-Write ETS/

8/15/79 E Billups 2/6/80 C Complete / Maine Yankee, Revise 10407 8/31/78 2/22/80 E Entire ETS/Cain 6977 6/22/78 10/27/77 6/15/78 12/15/79 E Complete / Point Beach-Review 5 years 6/13/79 8/22/79 9/15/77 T of Monitoring Data and Delete ETS Sections / Hickey 7424 4/5/78 7/13/79 C Complete / Millstone-Review winter 9/15/79 E flounder model/liickey 6/5/79 T 7626 12/20/77 6/19/79 C Complete /TMI unit 1-Adopt unit 2 6/15/79 E ETS/ Wilson 3/1/78 i NOTES:

1.

Key:

E= estimated completion date (assigned by ESB); T= target completion date (assigned by DDR); C= actual completion date for ESB input.

l'

/.i s

Page 2 ESB WORK SCHEDULE TECH SPEC (NON-RAD ENVIRON) CHANGES Licensee Date of RAI

Response

ESB Response TAC No.

TAC Receipt Issued Received to 00R Remarks /Amm. Ident./ Reviewer 7302 2/9/78 6/29/79 C Complete / Prairie Island-dredging 6/30/79 E and erosion control / Wilson 9/30/78 T Issued 1/22/80 6675 3/16/77 6/15/79 C Complete / Prairie Island-Revise 8/15/79 E makeup and blowdown rates / Wilson 5/1/77 T Issued 2/29/80 6947 7/26/77 8/25/78 C ESB Input Complete /TMI Unit 1-Delete 10/30/78 E certain programs / Wilson / Issued 10/15/77 T 1/28/80 7357 3/3/78 9/26/79 C Complete / Prairie Island-Review 8744 4/1/78 T Impingement data / Wilson / Issued 2/29/80 D

Page 3 ESB WORK SCHEDULE TECH SPEC (NON-RAD ENVIRON) CliANGES licensee Date of RAI

Response

ESG Response TAC No.

TAC Receipt Issued Received to D0R Remarks /Amm. Ident./ Reviewer 7465 4/13/78

' 11/21/79 C Complete / Response Being Coordinated 9/1/79 E with EPA /D.C. Cook Chlorine limits /

6/16/78 T Hickey 7779 7/26/78 8/15/78 7/16/79 C Complete / Quad Cities-Change 10/15/78 E Temperature monitoring /Cain 8/31/78 T 6963 7/77 5/78 5/79 1/28/80 C Complete / Beaver Valley 1-Extensive 6/30/78 T ETS Changes / Wilson / Issued 2/26/80 10391 11/24/78 1/22/79 4/27/80 E Waiting-EIA for incinerator con-struction/Nine Mile Point / Wilson 11194 1/9/79 4/11/79 C Complete / Crystal River /Cain 3/13/79 E l

~

Page 4 ESB WORK SCHEDULE TECH SPEC (NON-RAD ENVIRON) CilANGES Licensee Date of RAI

Response

ESB Response TAC No.

TAC Receipt Issued Received to D0R Remarks /Amm. Ident./ Reviewer 11447 2/14/79 Under Contract / Review 5-yr Moni-toring Results/Ft. Calhoun/Cain 4/27/79 C Complete / Crystal River /Cain 11009 4/11/79 5/4/79 T 10/15/79 E Waiting on changes to NPDES / Cook 1 11597 4/11/79 11598 7/9/79 T

& 2/ilickey 10/15/79 T Reduce monitoring program / Indian 11529 11530 Point Units 1-3/ Wilson 11531 1/14/80 C Comple, t/ Scouring & Thermal Plume 116604 4/26/79 11605 2/15/80 E 2 Mapping / Cook / Hickey 7/20/79 T 11538 4/19/79 4/18/80 E 3 Fish Impingement / Browns Ferry /

Billups O

6 e

Page 5 ESB WORK SCHEDULE TECH SPEC (NON-RAD ENVIRON) CHANGES Licensee Date of RAI

Response

ESB Response 1AC No.

TAC Receipt Issued Received to 00R Remarks /Amm. Ident./ Reviewer 11601 4/16/79 6/20/79 3/18/80 C Complete /Fi sh Impingement /Davi s 3/1/80 E2 Besse/ Hickey 5/15/79 T 11547 3/23/79 4/26/80 E3 Review Four Special Reports /Farley/

6/20/79 T Billups-Lehr 11504 3/5/79 7/3/79 10/15/79 C Complete / Vermont Yankee / Wilson 7/15/79 E 6883 4/13/79 Chemical decontamination /Dresden/

Wilson 5354 12/27/79 4/25/80 T EIS on Decon & Waste Disposal /

8/30/79 T TMI-Unit 2/ Hickey S

e

Page 6 ESB WORK SCHEDULE TECH SPEC (NON-RAD ENVIRON) CHANGES Licensee Date of RAI

Response

ESB Response TAC No.

TAC Receipt Issued Received to DDR Remarks /Amm. Ident./ Reviewer 11992 8/8/79 6/30/80 E1 Investigate Thermal Fish Kills /

11/11/79 T Oyster Creek /Masnik 11986 8/9/79 5/15/80 E Evaluate Envir. Monitoring Summary 11987 6/1/80 T Report / Zion / Wilson 11959 8/1/79 12/15/79 E Under Contract /5-yr Monitoring 2/1/80 T Programs / Cooper / Hickey 11935 7/19/79 4/30/80 E Changes to Monitoing Programs /

1/1/80 T Millstone /Masnik 3/31/80 C Complete / Delete LCO 's/St. Lucie/

11614-4/23/79 2/25/80 E Cain 7/1/79 T 12042 8/29/79 4/11/80 E2 Review of 5-year Monitoring 2/29/80 T Results/ Peach Bottom /Billups T

/

9

4 Page 7 ESB WORK SCHEDULE TECH SPEC (NON-RAD ENVIRON) CHANGES Licensee Date of RAI

Response

ESB Response TAC No.

TAC Receipt Issued Received to D0R Remarks /Amm. Ident./ Reviewer 11989 10/4/79 10/10/79 3/18/80 3/8/80 T Hearing on steam generator repair /

11990 Turkey Point / Wilson 11484 2/27/79 4/4/80 C Complete / Review of special studies /

3/15/80 El Crystal River /Cain 5/30/79 T 12390 11/7/79 12/6/79 C Complete / Cooling Tower Plume 12/1/79 E Report / Trojan / Gears 12/1/79 T 12454 11/9/79 3/15/80 E Impact on Shortnose Sturgeon / Hatch /

12455 3/15/80 T Wilson 12376 11/26/79 4/15/80 E ETS Changes-Thermal Measurements /

1/15/80 T San Onofre/Cain 5345 11/28/79 12/7/79 C Complete - Ecological Monitoring /

12/14/79 T Ft. St. Vrain/ Wilson / Issued 1/16/80 3/17/80 T Review entrainment program / San 12514 12/13/79 Onofre/Cain

Page 8 ESB WORK SCHEDULE TECH SPEC (NON-RAD ENVIRON) CHANGES Licensee Date of RAI

Response

ESB Response TAC No.

TAC Receipt Issued Received to D0R Remarks /Amm. Ident/ Reviewer

. 11672 12/12/79 3/1/80 T Deletion of Settling Plate Study /

San Onofre/Cain 11969 3/28/80 4/11/80 E Deletion of Certain Monitoring 9/1/79 T Requirements /Calvert Cliffs /

Cain 12869 2/22/80 5/15/80 T Delete Plankton Studies / San Onofre/Cain e