Ack Receipt of 800505 Ltr Requesting Walkdown of 10% of Class IE Equipment,Cables & Associated Circuits.More Complete Jan 1980 Walkdown Will Be Summarized in Fire Protection Program re-evaluation
ML19312E119
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 05/27/1980
From: Clayton F
ALABAMA POWER CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NUDOCS 8006030305
Download: ML19312E119 (2)


Text

.-- _ _ _ _ _ - - _ - _ - _ _ .

f Altbim3 Power CompIny

. 600 Nenh Ittn Street Post Offica Box 2641 Birmingham, Alabama 35291 Telephone 205 323-5341 F. L. CLAYTON, JR.

m  ;

Semor Vice President Alabama Power May 27, 1980 me swem eene swem Docket No. 50-364 Director of Nuclear Reactor Regulation Licensing Branch No. 2 U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Attn: Mr. A. Schwencer SEPARATION OF ELECTRICAL EQUIPMENT AND SYSTEMS FARLEY NUCLEAR PLANT - UNIT 2 Gentlemen:

Your letter of May 5,1980, requested that Alabama Power Company perform a walkdown of at least 10% of Farley Unit 2 Class lE equipment and cables and associated circuits for conformance to applicable separation criteria. It is the judgement of Alabama Power Company that a more encompassing walkdown was performed in January, 1980, in conjunction with the Fire Protection Program Reevaluation. This walkdown examined approximately 80% of the Class lE electrical equipment and cables and associated circuits for the following purposes:

1. Separation of redundant Class lE equipment.
2. Separation of redundant Class lE cables.
3. Separation of associated circuits (defined as circuits whose failure as a result of a fire could preclude operation of Class 1E cabling or equipment).

Note: Identification (markings) of Class lE equipment and raceways were utilized during the course of the walkdown and any identification discrepancies were noted and corrected.

This walkdown was performed by Bechtel Power Corporation upon directive by Alabama Power Company for the purpose of determining the type of fire protection necessary for all equipment, cabling, and circuits required for hot shutdown of the unit. This protection included sprinklers, rerouting cables, . installation of physical barriers, etc., for those cases where the fire separation criteria (20 feet for cables and equipment) was not met. Although Bechtel Power Corporation was involved in the design of these Class lE items, it is our position that the scope of this walkdown (80% c.f Class 1E systems) and participation by Alabama Power Company ensure its validity. OY 9

WD 800603o30f 8

Separation of Electrical Equipment Page 2 May 27, 1980 and Systems - Farley Nuclear Plant Unit 2 The results of this fire protection audit and any corrective actica for Unit 2 will be su=marized in the Farley Nuclear Plant Fire Protection Program Reevaluation.

If there are any questions concerning this response, please contact us.

Yours very truly,

^

1, .- -

F. L. Clayton, Jr.

FLCJr/ RLG:aw cc: Mr. R. A. Thomas Mr. G. F. Trowbridge