Georg'a Power Company y~y',

- 230 Peachtree Str:et 2

Post Offec; Box 4545 gggy Atlanta, Georgb 30302 6

Y>M

~ Telephone 404 622-6060 i

' E$,ilCt ?

~

L Power Generation Department March 4, 1980 Georgia Power l'i ? lg ;; "o, 0 I av U. S. Nuclear Regulatory Commission

REFERENCE:

Office of Inspection and Enforcement RII: JPO Region II - Suite 3100 50-321/50-366 101 Marietta Street I & E Bul. 79-23 Atlanta, Georgia 30303 Attention:

Mr. James P. O'Reilly Gentlemen:

Georgia Power Company hereby submits the following information in supplement to our letter of October 24, 1979, which was written in' response to your letter of September 12, 1979, transmitting Bulletin 79-23, " Potential Failure of Emergency Diesel Generator Field Exciter Transformer." In our October 24 response we noted that the sustained 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> full-load test for the Unit 1 emergency diesel generators would be performed by February 1, 1980. Those tests were successfully completed by January 13, 1980.

If there are further questions in this regard, please contact this office.

Sincerely, k), Q.

% (%/.LLk)

W. A. Widner Vice President and General Manager Nuclear Generation WEB /mj xc: