Responds to NRC Re Violations Noted in IE Insp Repts 50-498/80-07 & 50-499/80-07.Corrective Actions:Site Mechanical QA Instructed to Perform Surveillance of Installed Penetrations/Sleeves on Weekly Basis
ML19310A891
Person / Time
Site: South Texas  
Issue date: 05/23/1980
From: Eric Turner
HOUSTON LIGHTING & POWER CO.
To: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML19310A889 List:
References
ST-HL-AE-468, NUDOCS 8006300644
Download: ML19310A891 (2)


Text

['

(_)

The Light COmpy seastoa i.igating & Power R O. Box 1700 Houston. Texas 77001 (713) 228-9211 May 23, 1980 ST-HL-AE-468 SFN: C-0570 Mr. W. C. Seidle, Chief Reactor Construction 6 Engineering Support Branch U.S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76012

SUBJECT:

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION RESPONSE TO NRC INSPECTION FINDINGS DOCKET NOS. 50-498/80-07 AND 50-499/80-07

Dear Mr. Seidle:

The following is our response to the item of noncompliance identified in IE Inspection Report Nos. 50-498/80-07 and 50-499/80-07, dated April 30, 1980.

Failure to Follow Procedure for Storage of Material Corrective Action Nonconformance Report No. S-M3645 was generated to provide disposition for repairs to penetration M-39 in Unit 2 Reactor Containment Building (RCB-2).

Further surveillance of RCB-2 revealed other penetrations /

sleeves without proper end cover protection. Corrective Action Request No. S-285 was issued to Brown S Root Construction for violation of A040KPGCP-35, Revision 3, paragraph 3.6(6).

Recurrence Control Procedure A040KPMECP-4 will be revised to delineate specific surveil-lance requirements for mechanical penetrations / sleeves which require protection of machined end preps.

The anticipated date for release of this revision is July 15, 1980.

8006300 N

.. o

'Houdon Lighting & Power Company Mr. Seidle May 23, 1980 Page Two In the interim, Site Mechanical QA has been instructed by correspondence no. SQA-3708 to perform surveillance of installed mechanical penetra-tions/ sleeves which require protection of machined end preps on a once weekly basis. The once weekly surveillances will be documented on an Examination Check Form.

Very truly yours, A

h E. A. Turner, Vice President Power Plant Construction

& Technical Services EAT:rka cc: Messrs. G. W. Oprea, Jr.

M. L. Borchelt (CPL)

R. L. Range (CPLJ J. B. Poston (CPS)

A. vonRosenberg (CPS)

R. L. Hancock (COA)

M. C. Nitcholas (C0A)

H. R. Dean R. L. Waldrop C. L. McNeese D. G. Barker R. A. Frazar W. N. Phillips L. D. Wilson G. B. Painter M. D. Schwarz (Baker & Bott::)

C. G. Thrash (Baker S Botts)

H. S. Phillips (NRC)

J. R. Geurts (BSR)

C. W. Vincent (BSR)

STP RMS BSR DCC i

l

..